General comments:
- Road saws are all done
- We have raised the issue of the ‘thunking’ plates – this will be examined and the team will look to improve the final plating each night
- We have raised the issue of light tower placement to shine north/south as much as possible, rather than directly across the road
Tuesday night:
- Non Destructive Digging (NDD/Sucker Truck) until around midnight
- Excavator
- 4/5am install steel plates and move barriers
Note: If the team encounter crushed rock they may need to put on the hammer attachment on the excavator to loosen it up.
Wednesday night:
- NDD should be complete – but possibility they may need it if we get any water into the excavation
- Excavator
- Install conduits – by hand and glue together
- Install storm water pipes – installed with excavator (large concrete sections)
- 4/5am install steel plates and move barriers
Thursday night:
- Install conduit
- Install Storm water pipes
- 4/5am install steep plates and move barriers
Friday night:
- Tidy up
- Back fill
- Asphalt
Thanks, Rob