CYP update – Dec 1

Good afternoon everyone,

It is the first of December! 18 working day remain for 2023. We will be finishing up for the year on 22 December 2023. Monday is Picnic Day, so different than a RDO. Some trades will work, but not as many as a standard construction day.

Not a lot to report from the week that was. As you can imagine, we were slowed down quite a bit this week by the rain.

Upcoming major works: Toorak Road Resurfacing 5 to 7 December

The rain this week has delayed the completion of the southbound resurfacing works. These have been rescheduled to take place Tuesday, Wednesday and Thursday next week.

This requires an overnight road closure of St Kilda Road each night. We will complete the profiling, utility works and laying of the final wearing course.

More information regarding these works available here: https://bigbuild.vic.gov.au/__data/assets/pdf_file/0009/819414/MT-AZ-St-Kilda-Road-resurfacing-Dec-2023.pdf

Park Street to Albert Road

The rain has delayed the works in this stretch, installation of plants and furniture will continue next week.

Albert Road legacy construction

We have removed the sheds at Albert Road reserve. Next week we will reshuffle the site to allow us to work on the foundation of the South African Soldiers’ Memorial. We will also continue works on the legacy road which passes the Ramsay Clinic and the Domain building up to St Kilda Road.

Soft and hard landscaping continues in the linear park.

Linear park:

Albert Road Reserve forecourt and Station Entrance  (works until 1am)

The final pieces of the structural steel for the entrance are being installed today. Tomorrow and next week, the scaffolding will go up around the steel to commence the roof works. In ground services will be installed adjacent to the road, a very familiar formular. Underground, works continue for the walls and stairs of the Albert Road entrance.

Underground:

Station Fit out

Business as usual in Station fit out. Plenty of activity for the front of house and retail facilities. Back of house and B2 commissioning continues.

Eastern site – Shrine Entrance and Domain Road (Works until 1am)

For the entrance, the lift glass is in and glazed, construction on the lift cart and mechanics will kick off next week. Amongst all of the scaffolding, the gutters and the roofing are going in and will continue to do so next week.

The underground service installation is complete adjacent to the road. Earth and road works will continue next week. In December, we will shift traffic onto the new road.

On Monday night, South East Water works will take place from 10pm on Domain Road. These works must take place at night to reduce the impact of the water isolation, South East Water will contact affected customers.

St Kilda Road – Toorak Road to Bowen Lane

Northbound side (Towards City)

Works will continue behind the barriers as we install services, kerbs and prepare the garden beds. The team will spend next week preparing the site for line marking and barrier removal later in the month. 

St Kilda Road Bowen Crescent to Toorak Road (Night works)

Southbound side (Away from City)

This section was slowed down by the rain, we were quite lucky to make the progress that we did this week. We will have the pipes in across the laneway and the area backfilled on day shift today, allowing us to reopen the laneway tonight.

This will leave just the kerbs and the road surface remaining. We will undertake these works overnight at the same time as the asphalting works next week mentioned at the start of the email.

We are on track to remove the barriers from Bromby Street to Toorak Road and reopen the right turn from St Kilda Road to Kings Way late next week.

Have a great weekend,

Rob and Remy