Rough plan

  • Asphalting and turning on traffic lights at Albert Road
  • Asphalting at the northern end of the tram stop
  • Asphalting the footpath just past 412 SKR
  • Removing the barriers at Bowen Crescent and reopening the road
  • Working inside the Chillers

  • No loop cutting underway tonight
  • The footpath asphalting at 412 is early in the shift and should be done by midnight
  • They will backfill some of the trenched soil in the garden beds tonight – Have asked them to use hand tools.
  • Barrier removal will likely be just before the shift finishes
  • Also confirmed that the works inside the Chiller box will be finished tomorrow night
  • All the hybrid light towers have been serviced today and are fine