Building works – 24th onward

Hello all,

  1. Façade B & D:
    a. Next week, Avello will continue the painting works to these facades.
    b. Weather permitting, we hoping to complete painting works to these
    facades next week (excluding balcony internals & ground floor areas)
    c. Please ensure all windows and doors are closed for the duration of the
    painting works.
  2. Façade C (Rear):
    a. Depending on progress on Façade B & D, we expect to commence
    pressure washing & remedial works on this façade from Monday 31st
    March.
  3. Ground Floor / Front Retaining Walls:
    a. We expect to start works on these areas in the next few weeks.

    Please CLICK HERE to log any issues / defects on the Project Issues Register,
    which will be attended to by the project team.
    Thanks in advance for your cooperation and if you have any queries, please feel free
    to contact the building manager who will pass any information on the project team.
    Kind Regards,
    Fanus Coetzee
    Project Manager (For the OC Committee)
    Nick Waite
    Project Manager (For Avello Group)