Fortnightly Works Lookahead

Note to: All Residents
400 St Kilda Rd Melbourne
10/04/2025
Hello all,

  1. Façade B(Driveway):
    a. This façade is now complete (excluding balcony areas & ground floor
    areas).
  2. Façade D(Bowens cres):
    a. We hoping to complete painting works to this façade next week
    (excluding balcony internals & ground floor areas)
  3. Façade C (Rear):
    a. We will be commencing pressure washing & remedial works on this
    façade from Friday 11th April.
    b. Please remove as much as practically possible from your balcony,
    especially any fragile or easily damaged items.
    c. Please ensure all windows and doors are closed for the duration of the
    painting works, which is expected to be approx. 4 weeks.
  4. Ground Floor Areas / Front Retaining Walls:
    a. We expect to start works on these areas in the next few weeks.
    b. Next week we are planning to commence render repairs to the front
    retaining walls

    Please CLICK HERE to log any issues / defects on the Project Issues Register,
    which will be attended to by the project team.
    Thanks in advance for your cooperation and if you have any queries, please feel free
    to contact the building manager who will pass any information on the project team.
    Kind Regards,

    Fanus Coetzee
    Project Manager (For the OC Committee)

Nick Waite
Project Manager (For Avello Group)