  1. Façade C (Rear):
    a. Pressure washing and painting works on the balconies are currently in
    progress. These works are taking slightly longer than anticipated, but
    we expect completion within approximately one week.
    b. To assist us in accessing all areas—including balcony floors—please
    ensure all personal items are removed.
    c. If you require assistance moving items, please CLICK HERE to log a
    request, and a team member will be in touch.
    d. Subject to weather conditions, works on this façade are expected to be
    fully completed within the next two weeks.
  2. Façade A (Front):
    a. We are scheduled to commence pressure washing and remedial
    repairs on this façade from mid to late this week.
    b. We kindly ask residents to remove any fragile or easily damaged items
    from balconies. We will provide further notice when we are ready to
    clean and paint the balcony floors.
  3. Front Retaining Walls:
    a. These walls will have cracks filled and painting completed once Façade
    A is complete.
  4. Weather:
    a. We have been fortunate with dry weather to date, although conditions
    will likely change soon. We appreciate your patience and
    understanding while we deal with weather-related delays.

    To log any project-related issues or defects, please CLICK HERE to submit them via
    the Project Issues Register. The project team will ensure they are addressed
    promptly.
    Thank you in advance for your cooperation. Should you have any questions, please
    feel free to contact the building manager, who will liaise directly with the project
    team.
    Kind Regards,
    Fanus Coetzee
    Project Manager (For the OC Committee)
    Nick Waite
    Project Manager (For Avello Group)

Leave a comment