Painting works lookahead

Note to: All Residents
400 St Kilda Rd Melbourne
17/07/2025
Hello all,

  1. Winter Weather:
    a. We are being heavily impacted by the winter weather which is delaying
    and changing our schedule. We appreciate your patience and
    understanding while we deal with weather-related delays.
  2. Façade C (Rear):
    a. Painting works on the open balconies is nearing completion, however
    are being delayed due to wet / cold weather. We will be completing this
    work as soon as the weather allows.
    b. Please take care when moving items on your balcony, as the paint will
    be soft for several weeks and easily damaged.
  3. Façade A (Front):
    a. Remedial repairs to the main façade have commenced and we expect
    to commence painting main façade areas shortly.
    b. Prior to starting works on enclosed balcony areas, we will provide
    notice so these areas can be cleared accordingly.

    To log any project-related issues or defects, please CLICK HERE to submit them via
    the Project Issues Register. The project team will ensure they are addressed
    promptly.

    Thank you in advance for your cooperation. Should you have any questions, please
    feel free to contact the building manager, who will liaise directly with the project
    team.

    Kind Regards,
    Fanus Coetzee
    Project Manager (For the OC Committee)
    Nick Waite
    Project Manager (For Avello Group)