Painting works 28th-8th

Note to: All Residents
400 St Kilda Rd Melbourne
25/07/2025
Hello all,

  1. Winter Weather:
    a. We are being heavily impacted by the winter weather which is delaying
    and changing our schedule. We appreciate your patience and
    understanding while we deal with weather-related delays.
  2. Façade C (Rear):
    a. Painting works on the open balconies is nearing completion, however
    are being delayed due to wet / cold weather. We will be completing this
    work as soon as the weather allows.
  3. Façade A (Front):
    a. Remedial repairs to the main façade are well underway and we expect
    to commence painting main façade areas shortly.
    b. Prior to starting works on enclosed balcony areas, we will provide
    notice so these areas can be cleared accordingly.

    To log any project-related issues or defects, please CLICK HERE to submit them via the Project Issues Register. The project team will ensure they are addressed promptly.
    Thank you in advance for your cooperation. Should you have any questions, please feel free to contact the building manager, who will liaise directly with the project team.

    Kind Regards,
    Fanus Coetzee
    Project Manager (For the OC Committee)
    Nick Waite
    Project Manager (For Avello Group)