Painting works lookahead – Front and Back Facade

Note to: All Residents
400 St Kilda Rd Melbourne
11/08/2025
Hello all,

  1. Façade A (Front):
    a. Remedial Repairs & Painting to the main façade are well underway.

    b. The replacement Window Headers have arrived and will be installed as soon as practical.
  2. Units 104-703 Balconies (Façade A/D Corner):
    a. We are planning to commence pressure washing and painting works
    on these balconies on Monday 18th August and expect works to take
    approx. 2-3 weeks.

    b. Please ensure all items are removed from the balcony so we can
    clean and paint all areas including the floors.

    c. If you require assistance to remove items, please CLICK HERE to log
    your issue and someone will be in contact.
  3. Façade C (Rear):
    a. We expect to be completed painting works to this façade in the next 1
    2 weeks (weather dependent).


    To log any project-related issues or defects, please CLICK HERE to submit them via the Project Issues Register. The project team will ensure they are addressed promptly.

    Thank you in advance for your cooperation. Should you have any questions, please feel free to contact the building manager, who will liaise directly with the project
    team.


    Kind Regards,
    Fanus Coetzee
    Project Manager (For the OC Committee)
    Nick Waite
    Project Manager (For Avello Group)

Leave a comment