Works on the driveway have been significantly delayed due to the rain the last two weeks.
Thursday 6 and Friday 7 July are forecast to be clear until the afternoon permitting us to complete the works required.
We will close the driveway from 9am to 4pm each day on Thursday 6 and Friday 7 July.
If you have any questions or concerns regarding the driveway closure or any access requirements, please do not hesitate to reach out by calling 1800 105 105 or via email at CYP@metrotunnelcyp-dc.com.au
I apologise for the inconvenience caused by these shifting dates. We are aiming to complete these works as soon as possible and will continue to provide updates as soon as they become available.
Happy last day of June, hard to believe we are moving into the second half of the year tomorrow!
Over July, there will be quite a bit of night works in all sections of the job. Works in the station box and station entrances, road works on St Kilda Road including utility connection, tram lights and pole installation, barrier moving, signal connections, and line marking will all take place at night in July.
You may have also noticed CitiPower have been working on the corner of Park Street and St Kilda Road overnight. I have been in touch with them, they are due to complete works on 6 July, if you have any questions or concerns you can reach them at MajorProjects@powercor.com.au or by calling 1300 301 101.
Things are ticking along, here a look at what is happening next week and beyond.
Utility Works – Bowen Lane to Bowen Crescent
Next week in this area we will be working away to complete the station sewer and water connections. The pedestrian diversion I mentioned last week which will shift pedestrians away from Bowen Lane and closer to St Kilda Road (think current arrangement at Park Street to Albert Road) will be in place from 11 July. Pedestrians moving from Bowen Lane to Bowen Crescent will see a longer walk as they will be required to walk around the site. A traffic plan outlining this is at the bottom of this email.
Albert Road Reserve Station entrance
This week, we poured the first section of the base slab in the Albert Road entrance.
Formwork, steel fixing and concrete pours will continue as we complete section by section. As mentioned above, we will be working in the station entrances at night.
Albert Road North construction
No major updated here. Works on the Kings Way end of Albert Road have been a focus for this area and will continue to be into next week. Breakout and demolition of the redundant roadway continue as well as the construction of the legacy linear park. The team are working away to reopen the westbound lane of Albert Road out to Kings Way as soon as possible.
St Kilda Road median works – South
Median works are continuing between Bowen Cres and Toorak Road. The pedestrian crossing at the southern end of the tram stop is on track to reopen in mid-July as planned. We have added some more fencing and signage to this area to help pedestrians get around.
The permanent parking removal on both sides of St Kilda Road and the construction of the separated bike lanes will take place in July. There will be night works in mid-July to move the barriers to make this possible. We will need to reduce the northbound lane of St Kilda Road to one lane in this section to facilitate these works. You will see some changes to the traffic arrangement and line marking from as far down as Arthur Street.
Largely, the site set up will look a lot like it does now between Park Street and Dorcus where a similar scope is taking place. We are aiming to complete the eastern side of St Kilda Road by the end of July, but with the winter rain and encountering some unexpected services, we are trying to make back delays.
St Kilda Road median works – North
No new updates in this area, works continue to progress well and are on track to reopen mid-July.
Station box construction
Testing, commissioning, installation all continues in the station box. Platform screen door testing, commissioning of the lifts, colour back glass installation, drum lights, back-of-house room fit-out, are ongoing. In July, we will start installing the legacy flooring in some sections of the station.
Shrine Entrance
Not a whole lot to update at the Shrine Entrance, a mountain of work is taking place for the raft slabs and columns. Installation of the new walkway and hoarding is ongoing.
Park Street to Albert Road
Rectification works in this area are ongoing and will continue into next week. There will be works in the service pits in front of the Domain Hill on Tuesday which will detour pedestrians around the site.
As mentioned in my email earlier in the week, the works scheduled for Wednesday were unable to take place. The rescheduled date for this works is Monday 3 July from 8am to 4.30pm.
In light of the difficulties faced this week, I wish to inform you that there is potential for these works to run over into Tuesday 4 July from 8am to 4.30pm as well. All efforts will be made to avoid this, however if unexpected challenges are encountered, please be aware of this additional date.
If you have any questions or concerns regarding the driveway closure or any access requirements, please do not hesitate to reach out by calling 1800 105 105 or via email at CYP@metrotunnelcyp-dc.com.au
Again, I apologise for the inconvenience caused by these shifting dates.
We will continue to provide updates as soon as they become available.
This came through from the Melbourne South Yarra Residents group (MSYRG) this morning.
Members and neighbours have informed MSYRG that this week there have been at least two assaults of women in Millswyn Street. It is a man targeting women specifically between 7-8am in the mornings.
The police have been informed.
If you have seen anything that might help the police investigation, please call the police on 1800 333 000
I am writing to provide you with an update regarding the planned driveway closure that was scheduled for today, Wednesday 28 June 2023. Unfortunately, due to unforeseen issues with our subcontractor and inclement weather conditions, we encountered some unexpected delays that prevented us from proceeding as initially planned.
I understand that this may cause inconvenience and frustration and apologise for the disruption this may have caused to your daily routine.
The driveway closure will take place tomorrow, Thursday 29 June as planned.
We still require a second day of driveway closure to complete the works. This will likely be Monday 3 July, 2023. This will be confirmed tomorrow at the latest.
If you have any questions or concerns regarding the driveway closure or any other related matter, please do not hesitate to reach out by calling 1800 105 105 or via email at CYP@metrotunnelcyp-dc.com.au
Again, I apologise for any inconvenience caused by these unforeseen circumstances. We will continue to provide updates as soon as they become available.
While it was freezing this week (at least for a Darwin expat such as myself), it is nice to know that now the winter solstice (shortest day of the year for daylight hours) has come and gone, and we will slowly but surely, start to get a bit more daylight.
Monday 26 June is a rostered day off, so the majority of the crews will be back from the weekend on Tuesday. Here is a bit of an update on completed works and what is upcoming.
Utility Works – Bowen Lane to Bowen Crescent
Utility works in this area are set to really ramp up over the next few weeks. We are installing a watermain under St Kilda Road, close up against the footpath. There will be a few pedestrian diversions (similar to what has been seen around the Hallmark and Domain Hill) and access changes to buildings in this area. We will keep the information coming regarding this future changes.
Albert Road Reserve Station entrance
This station entrance will look largely the same for the next little while. Waterproofing is complete. Formwork, steel fixing and concrete pours are ongoing. As works at the entrance progress (much like on the Shrine side), night works will take place in the station around the Albert entrance.
Albert Road North construction
Works on the Kings Way end of Albert Road have been a focus for this area and will continue to be into next week. Breakout and demolition of the redundant roadway continue as well as the construction of the legacy linear park.
St Kilda Road median works – South
We will start service proving on the city bound side of St Kilda Road from Tuesday. This will help inform our construction methodology before works on the drainage and installation of the separated bike lanes commence here on 5 July. Once these works commence, the permanent parking removal as highlighted in yellow on the map below will be in place.
St Kilda Road median works – North
No new updates in this area, works continue to progress well and are on track to reopen mid-July.
Station box construction
Testing, commissioning, installation all continues in the station box. Platform screen door testing, commissioning of the lifts, colour back glass installation, drum lights, back-of-house room fit-out, are ongoing.
Shrine Entrance
Walls and column installation that divide the front and back of house in the entrance are underway as I mentioned last week. Installation of the new walkway and hoarding are ongoing, moving the hoarding will allow us to commence the next stage of works in this area. We will be connecting the water and power to mains this Sunday during the day.
Park Street to Albert Road
We will be coming back to work on the recently opened new footpath this area on Tuesday to undergo some rectification works. The previous pedestrian arrangement that was implemented in May will be in effect. Pedestrians on the southern footpath of St Kilda Road will be diverted onto a temporary footpath on the roadway while the footpath works take place. As with last time, pedestrian access to Domain Hill and The Hallmark maintained at all times.
You must be logged in to post a comment.