Great to see the weeding being done – this seems to think it is already complete 🙂
Good afternoon all,
Welcome to this week’s construction update for the Domain Precinct and Anzac Station.
Anzac Station has been in the news this week, with the announcement of completion of major construction work. The station platform and concourse level are complete and looking great – we’re in the testing and commissioning phase of the systems that will be needed for day one operation.
We’re also quickly approaching the finish line for the surface works too – with the final paving and asphalting happening around the site. The one-way road connection between the driveway for 1 Albert Road (The Domain) and St Kilda Road will open next week (Thu 19 Sept) – and the reopening of Domain Road to traffic is on track for mid-October.
Onto the ever-shrinking list of works for next week:
Overnight Works:
No overnight works planned.
Works next week
Albert Road Reserve forecourt and Station Entrance
The focus for next week will be the completion of the cladding on the terrace seating leading down to the reserve. Once that is done, it will primarily be an exercise in landscaping – with much of the topsoil already being trucked into site.
Shrine Entrance and Domain Road
The pavers have wasted no time in laying down bluestone over at the Shrine entrance – and with the completion of curbs along the edge – the entrance has very quickly transformed from a dirt patch, into to a station forecourt.
Up Domain Road, the team will switch from the heavy asphalting works of this week, to the installation of tactiles on the dual bus/tram stop, and eventually move onto street furniture installation over the coming weeks.
Next week we’ll have some works to connect in the final lighting along Domain Road, which will be followed shortly after by the final layer of asphalt along the southern footpath.
Edmund Herring Oval (EHO) Reinstatement
Edmund Herring Oval continues to tick over, with much of the focus on the reinstatement of the heritage stone wall around the perimeter of the oval. These works continue next week.
Rectification Works
With the heavy works nearly complete up on Domain Road, we’ll be putting resources into the rectification works around site. Today we completed weeding between Bowen Crescent and Bowen Lane, and some of these finishing touches will continue over the coming weeks. The repair works on the bluestone pavers at the top of Albert Road near St Kilda Road are still on our radar – we may have to water blast off the wax that skateboarders have used to facilitate better board slide on the bluestone. We’re just working through a plan for this now. Once that is done, we’ll immediately install the skate deterrents on the bluestone.
Friday Flashback
I thought this week we’d travel back to one of the first batch of photos in our archive – the 2018 construction of the new track alignment for the trams on St Kilda Road. This relocation of the tram tracks and road enabled the start of main works.
Following two more tram realignments, construction and destruction of an acoustic shed, the assembly and launch of TBMs to the north and then to the south – we’re now in sight of the finish line for major construction – and looking forward to train passenger services in 2025.
Have a wonderful weekend!
Thanks, Rob


You must be logged in to post a comment.