All posts by botanicaconcierge

Building works from 28th-9th

Note to: All Residents
400 St Kilda Rd Melbourne
24/04/2025
Hello all,

  1. Façade C (Rear):
    a. We are progressing with pressure washing and remedial & painting
    works on this façade.
    b. Please remove as much as practically possible from your balcony,
    especially any fragile or easily damaged items.
    c. Please ensure all windows and doors are closed for the duration of the
    painting works, which is expected to be approx. 4 weeks.
  2. Façade C/D Corner Balconies (Rear/Bowen Cres Corner):
    a. We are planning to commence pressure washing and painting works
    on these balconies on Monday 5th May and expect works to take
    approx. 1 week.
    b. Please note, we need all items to be removed from the balcony so we
    can clean and paint all areas including the floors.
    c. If you require assistance to remove items, please CLICK HERE to log
    your issue and someone will be in contact.
  3. Ground Floor Areas / Front Retaining Walls:
    a. Render repairs to the front retaining walls are underway.
    b. We expect to start painting works on these areas in the next few
    weeks.

    Please CLICK HERE to log any issues / defects on the Project Issues Register,
    which will be attended to by the project team.

    Thanks in advance for your cooperation and if you have any queries, please feel free
    to contact the building manager who will pass any information on the project team.

    Kind Regards,
    Fanus Coetzee
    Project Manager (For the OC Committee)
    Nick Waite
    Project Manager (For Avello Group)

Resident & Council Meet and Greet

Thursday June 5th 6pm-8pm
Flo’s Cafe 412 St Kilda Road

Guest Speaker: Beti Jay
Councilor of the South Melbourne ward

There will be a short info session and questions for Beti about council matters and the chance to get to know our local councilor.

To assist in catering, please rsvp to Reeve or Margaret by Monday June 2nd

Reeve: 0467 444 074
Margaret: knurekmusic@gmail.com

For Sale: Fiat 500

Car Details

  • Make: Fiat 500
  • Year: 2011
  • Mileage: 143000 km
  • Colour: Red
  • Transmission: 5 speed manual
  • Bluetooth Connectivity

Car is in great condition, regularly serviced, no accidents.

It’s a great little run around for the city, easy to park and economical on fuel.

Price

$7,500 (negotiable)

Contact Information

  • Name: Veronica (Apt 604)
  • Phone: 0417287600

Fortnightly Works Lookahead

Note to: All Residents
400 St Kilda Rd Melbourne
10/04/2025
Hello all,

  1. Façade B(Driveway):
    a. This façade is now complete (excluding balcony areas & ground floor
    areas).
  2. Façade D(Bowens cres):
    a. We hoping to complete painting works to this façade next week
    (excluding balcony internals & ground floor areas)
  3. Façade C (Rear):
    a. We will be commencing pressure washing & remedial works on this
    façade from Friday 11th April.
    b. Please remove as much as practically possible from your balcony,
    especially any fragile or easily damaged items.
    c. Please ensure all windows and doors are closed for the duration of the
    painting works, which is expected to be approx. 4 weeks.
  4. Ground Floor Areas / Front Retaining Walls:
    a. We expect to start works on these areas in the next few weeks.
    b. Next week we are planning to commence render repairs to the front
    retaining walls

    Please CLICK HERE to log any issues / defects on the Project Issues Register,
    which will be attended to by the project team.
    Thanks in advance for your cooperation and if you have any queries, please feel free
    to contact the building manager who will pass any information on the project team.
    Kind Regards,

    Fanus Coetzee
    Project Manager (For the OC Committee)

Nick Waite
Project Manager (For Avello Group)

Building works from April 7th

Hello all,

  1. Façade B (Bowen Cres:
    a. This façade is now complete (excluding balcony areas & ground floor
    areas).
  2. Façade D (Lower carpark driveway):
    a. Weather permitting, we hoping to complete painting works to these
    façade in the next 1 week (excluding balcony internals & ground floor
    areas)
    b. Please ensure all windows and doors are closed for the duration of the
    painting works.
  3. Façade C (Rear):
    a. We will be commencing pressure washing & remedial works on this
    façade from Tuesday 8th April.
    b. Please remove as much as practically possible from your balcony,
    especially any fragile or easily damaged items.
    c. Please ensure all windows and doors are closed for the duration of the
    painting works, which is expected to be approx. 4 weeks.
  4. Ground Floor / Front Retaining Walls:
    a. We expect to start works on these areas in the next few weeks.
    Please CLICK HERE to log any issues / defects on the Project Issues Register,
    which will be attended to by the project team.
    Thanks in advance for your cooperation and if you have any queries, please feel free
    to contact the building manager who will pass any information on the project team.
    Kind Regards,

Fanus Coetzee
Project Manager (For the OC Committee)

Nick Waite
Project Manager (For Avello Group)

Carpark Closure 3rd+4th and other upcoming works

Note to: All Residents
400 St Kilda Rd Melbourne
01/04/2025
Hello all,

  1. Façade B:
    a. This façade will be complete by Wednesday 2nd April (excluding
    balcony areas).
    b. On Thursday 3rd April & Friday 4th April access to the lower carpark will
    be blocked between 9am-4.30pm to enable dismantle of scaffolding. If
    you do need to use your vehicle, please ensure this is removed from
    the carpark prior to 8.30am. (We apologise for the short notice;
    however, we understand that the removal of the hoarding is a priority)
  2. Façade D:
    a. Weather permitting, we hoping to complete painting works to these
    façade in the next 2 weeks (excluding balcony internals & ground floor
    areas)
    b. Please ensure all windows and doors are closed for the duration of the
    painting works.
  3. Façade C (Rear):
    a. We expect to commence pressure washing & remedial works on this
    façade during next week.
  4. Ground Floor / Front Retaining Walls:
    a. We expect to start works on these areas in the next few weeks.

    Please CLICK HERE to log any issues / defects on the Project Issues Register,
    which will be attended to by the project team.
    Thanks in advance for your cooperation and if you have any queries, please feel free
    to contact the building manager who will pass any information on the project team.

Building works – 24th onward

Hello all,

  1. Façade B & D:
    a. Next week, Avello will continue the painting works to these facades.
    b. Weather permitting, we hoping to complete painting works to these
    facades next week (excluding balcony internals & ground floor areas)
    c. Please ensure all windows and doors are closed for the duration of the
    painting works.
  2. Façade C (Rear):
    a. Depending on progress on Façade B & D, we expect to commence
    pressure washing & remedial works on this façade from Monday 31st
    March.
  3. Ground Floor / Front Retaining Walls:
    a. We expect to start works on these areas in the next few weeks.

    Please CLICK HERE to log any issues / defects on the Project Issues Register,
    which will be attended to by the project team.
    Thanks in advance for your cooperation and if you have any queries, please feel free
    to contact the building manager who will pass any information on the project team.
    Kind Regards,
    Fanus Coetzee
    Project Manager (For the OC Committee)
    Nick Waite
    Project Manager (For Avello Group)