Building works from April 7th

Hello all,

  1. Façade B (Bowen Cres:
    a. This façade is now complete (excluding balcony areas & ground floor
    areas).
  2. Façade D (Lower carpark driveway):
    a. Weather permitting, we hoping to complete painting works to these
    façade in the next 1 week (excluding balcony internals & ground floor
    areas)
    b. Please ensure all windows and doors are closed for the duration of the
    painting works.
  3. Façade C (Rear):
    a. We will be commencing pressure washing & remedial works on this
    façade from Tuesday 8th April.
    b. Please remove as much as practically possible from your balcony,
    especially any fragile or easily damaged items.
    c. Please ensure all windows and doors are closed for the duration of the
    painting works, which is expected to be approx. 4 weeks.
  4. Ground Floor / Front Retaining Walls:
    a. We expect to start works on these areas in the next few weeks.
    Please CLICK HERE to log any issues / defects on the Project Issues Register,
    which will be attended to by the project team.
    Thanks in advance for your cooperation and if you have any queries, please feel free
    to contact the building manager who will pass any information on the project team.
    Kind Regards,

Fanus Coetzee
Project Manager (For the OC Committee)

Nick Waite
Project Manager (For Avello Group)