Water cut off , cancelled today
They will do on Wednesday and Thursday
New pamphlets on table outside lifts
Water cut off , cancelled today
They will do on Wednesday and Thursday
New pamphlets on table outside lifts
What a beautiful day! Spring really is just around the corner.
The precinct has seen a lot of change over the last week. We have removed the barriers from Dorcas to Park street, reopening the Kings Way slow lane, shifted the barriers between Park Street and Melbourne Grammar School to start the legacy road work and have begun the two week closure of Albert Road at the St Kilda Road end.
Next week will be just as busy, lets take a look at what is coming up.
We are getting ready to rebuild the kerbs and roadway of Bowen Lane. You will have noticed a common theme in these weekly updates, largely being that we’re having a lot of trouble with services in this area. Unfortunately Bowen Lane won’t open by the end of the month, it is now looking more like 9 September. We will let you know how this is tracking next week.
Nothing new to report in the station entrance, it’s more of the same as the team continue the steel fixing and concrete pours for the station walls. We have poured seven of the walls so far, we’ve included a picture of the formwork below.
Just as this week, next week a lot of energy and resources will be sent to Albert Road.
I hope everyone is getting around the site and the pedestrian detours ok. There will be some changes over the weekend so keep an eye out for updated signage as you make your way through the site. From Monday the final driveway will close and will have access to the full works area.
Next week:
This closure will be in place until 7 September.
On the southbound side, works to investigate and prepare the site have been going well. The team will start to trench from next week and install the drainage pieces.
On the other side of the road, drainage install will continue next week and then the team will move onto installing the separated bike lanes and reinstating the road.
A new compound was intended to be set up earlier in the week south of Kings Way / Toorak Road but these have been rescheduled to Tuesday 29 August. The new site will be in place for about six weeks where we will, again, install new drainage and separated bike lanes. One night of works is required to move barriers into place, then day works only until we need to remove the barriers. A closure of St Kilda Road northbound is required for these works.
You may have noticed the barrier free area between Dorcas and Park. It is looking very green in the northern end of the job. We will still be hanging around this area to finish a few things off. The pedestrian east / west crossing at Park and St Kilda Road will need to close for a few days sometime soon to allow the finishing touches.
The station works remain fairly consistent, with granite paving going down on the train platform and the fitout works for individual rooms continuing on the concourse level. A picture of the paving is below.
Today we poured the first section of the stairs at the Shrine entrance! Below is a picture of the before, we will include an after shot in next weeks update.
No new action in this area – We’ll provide an update when the trees are scheduled to be planted in this section of the job.
Have a great weekend
Rob and Remy




I called the 1800 number at 3am to get it stopped
Be aware that there will be some abseilers on the front of the building tomorrow. They are remediating the facade work that was done last year. It will may involve some cutting / caulking / painting.
Sorry for the short notice

I hope everyone has managed to stay dry today. The downpour has put a bit of a dent into progress today, but it has been a good week out on site generally.
Just a reminder that next Monday is an RDO – but once we return we head into a big week of construction.
Let’s dive into it.
It’s been a bit of a slog down in this section of the job, but we’re finally done with the water and we’re onto the installation of the new drainage through this area. Next week we’ll start the excavation for the drainage run and that will dominate activity during the week.
Nothing new to report in the station entrance, it’s more of the same as the team continue the steel fixing and concrete pours for the station walls.
This is where all the resources and action will be next week, with some big traffic changes put in place
We’ll then commence the full rebuild of Albert Road (roughly from Kettle Black up to St Kilda Road)
As you’re walking around the site, please be aware that there will also be multiple stages of pedestrian detours as we work our way through each of the stages of work.
Two of the big changes you’ll see during the works are:
Keep an eye out for the updated signage as you make your way through the site.
In terms of the actual works – the work kicks off in earnest on Thursday next week, and includes:
We’re now well underway in the section of outbound road between Bromby Street and Toorak Road, this week the team pulled up the pitchers in the kerb and started with some good progress on the trench excavation. Next week the drainage pipes will arrive and will be installed as the trench excavation advances.
On the city bound side of the road, it’s much of the same scope of works, however the trench is largely excavated and the team are already underway laying the new drainage pipes.
One development at this end of the job was the new turf installed in the median – a sure sign that we’re getting closer to the finish line for roadworks.
There is a bit of work going on overnight this week, but nothing that would be considered overly disruptive.
On Wednesday night the barriers will be removed from the outbound lane of St Kilda Road between Dorcas and Park Street some line marking will take place to return traffic and bikes to the outer lane.
On Thursday night we’ll then shift some of the barriers in the outbound lane next to the tram stop, this will allow us to get in and start the utilities work in this section of the site – which will ultimately lead to the construction of the second lane of traffic through this section.
The section of St Kilda Road between Park and Dorcas will have a whole new look, as for the first time there are no barriers separating one side of the road from the other.
The station works remain fairly consistent, with granite paving going down on the train platform and the fitout works for individual rooms continuing on the concourse level.
The work on the pre-cast stairs for the Shrine entrance made some good progress this week and will continue in the following week. We’ll include a photo in the coming editions, as the completion of these stairs will be a nice mini-milestone.
No new action in this area – We’ll provide an update when the trees are scheduled to be planted in this section of the job.
Have a great weekend
Rob and Remy


An owner in the building needs an extra bay – suitable for a Landcruiser.
If you can help call Jane on 0411 094 068

If you asked to have a free plumbing check, can you talk to Paul to lock in an approximate time.
The checks will happen next Tuesday and Wednesday August 22/23
They will take less than 30 minutes
If you didn’t request a check and have changed your mind, tell Paul and you can be on the backup list. They will do you at the end if they have time
If you asked to have a free plumbing check, can you talk to Paul to lock in an approximate time.
The checks will happen next Tuesday and Wednesday August 22/23
They will take less than 30 minutes
If you didn’t request a check and have changed your mind, tell Paul and you can be on the backup list. They will do you at the end if they have time
Currently there is an interruption to our water supply associated with works at Bowen Lane. Should be restored by 5.00-5.30pm 🤞
You must be logged in to post a comment.