Category Archives: Metro Rail

MMRA – Community Reference Groups

I represent Botanica on the Metro Rail Community Reference group for the Domain Precinct.  We have only had a couple of meetings and are still getting the processes working – but I am really pleased that they now have a web site that contains the minutes and presentations.

Meetings are held about every 6 weeks

The web site is here and you can see the documents for the Domain precinct and other precincts.

Repairing cocky damage

You may have seen guys abseiling on the Bowen Cres side of Botanica on Friday.  As all residents would know, we have had a long standing battle with cockatoos and their sharp beaks.  We are about to run a trial of some new harder material.

Last week they removed one section, next week they will install the new material.

P1030612xP1030614x

Our poor footpath

Who would have thought that less than one week after our footpath was re-instated and re-surfaced, they have dug it up again…and have had to use their graffiti AGAIN.  You’d think they could have checked what is under the asphalt when it was dug up??

20171020_173547P1030605

Bowen Cres eastbound closed

I received this from MMRA…don’t think it was in the letterbox drop, not sure why??

On Monday and Tuesday Bowen Crescent eastbound lane will be closed adjacent your premise for gas works. The gas works contractor will ensure access to your driveway will be maintained and I have tool boxed our traffic controllers on their interaction with vehicles entering and exiting your building and ensuring support is provided.

 

Comms work update

The sad state of our footpath will improve over the next 10 days.  Next week they will backfill most of the trenches, leaving two smallish holes.

They are trying to re-instate our parking bays as soon as possible – my guess is the end of next week.

You should also be aware that there will be quite a lot of action in Bowen Cres over coming weeks.

  • Monday Oct 2 – Westbound traffic stopped for gas commissioning
  • Mid-Oct to mid-Dec (my guesses) – they need to make two pits in Bowen Cres, near St Kilda Rd.  From those pits they will push drainage and sewer pipes under St Kilda Rd.  Will be done during the day and the company contracted to do the work has converted all their vehicles from reversing beepers to less intrusive squawkers

We do NOT expect any driveway access issues in Bowen Cres – you may need to patiently wait for the traffic control to let you through.