As the residents of Botanica will have noticed, there is lots of work happening. The current plan (subject to change of course) is as follows:
- Gas work next to the Bowen Cres driveway will be done this week.
- Involves laying a concrete slab, installing a meter and cage
- Garden will be re-instated at the end, as best it can be
- We are likely to have a gas outage on Thursday during the day
- Comms work under footpath
- Most of the ‘work’ should be done by the end of this week
- Footpath re-instatement should be done by end of next week