Lots of tunnel news and pictures

Some of the main points to note

  • The trucking company is now using some decent tracking. It allows them to track a truck going ‘off approved routes’ and to detect speeding trucks. They noted that it has changed the behaviour of the drivers
  • The first TBM will commence before Xmas and finish in May.
  • Second TBM will commence in February and finish in late June
  • This means that the period of two TBMs is Feb-May
  • Work / meetings are happening this week to avoid unacceptable vibration when two TBMs are running
  • Public discussion on legacy design (including Chiller plants) will not happen this year.
Advertisement

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s