A very detailed pack below. Some details
- The VERY noisy occupation period will be from 1am Sunday November 27
- The first 2-3 days will be the worst, but all three weeks will be noisy and 24*7 hour
- There will be no trams operational and a bus replacement system. We will get more detail closer to the time
- The cladding on our vents may happen before the occupation
- If we have a lot of wet weather, then we there may be overnight work in the period November 7-19
Also worth noting is the efforts with new trees. You can see from this image that there will be trees on the platform

To assist their growth (on top of the concrete station roof) they have installed what is called Strata Vault. See below.