
This is still the plan for trees – five in front of us (I think they are waiting for the garden to become established before digging it up), two in front of 390 SKR and 10-11 in the middle near the chillers.
Here is a close up of our section


This is still the plan for trees – five in front of us (I think they are waiting for the garden to become established before digging it up), two in front of 390 SKR and 10-11 in the middle near the chillers.
Here is a close up of our section

No word on our parking bays out the front
No word on trees in the middle or out the front
No word on releasing the parking bays in Albert Rd
No word on the wrong sign
…..and have a good long weekend – surely not another one?!?!?!
Overnight Works:
The only possible nightworks next week is some minor line-marking works on St Kilda Road. The team wont need to close any roads or driveways, so they’ll take the opportunity when the weather is right from Sunday next week. The works are minor and aren’t expected to generate any disturbance.
Looking further ahead, we will have some overnight works in the first week of July. This is the asphalting of the left turn from St Kilda Road into Domain Road.
While we’re out and about that night, we’ll also install the permanent tactiles at the south western pedestrian crossing to the tram stop (near Bowen Lane) as well as remove the temporary fencing that runs alongside the tram tracks.
Works next week
Albert Road Reserve forecourt and Station Entrance (Works until 1am)
I’m running out of interesting ways to say that we’ll be doing bluestone paving, but rest assured, there is more bluestone paving ahead of us.
Elsewhere though, we’re about to start work on a retaining wall that delineates Albert Road South from the station concourse. This started this week and will continue into next week, with some formwork and concrete pours.
Meanwhile, the South African Soldiers’ Memorial continues to make its way upward.
Shrine Entrance and Domain Road (Works until 1am)
At the Shrine entrance, its more of the same, with breakout of the concrete working surface adjacent to the new lift shaft. This area has cleared out nicely though, and we’ll begin the surface preparation shortly for the new footpath connection into the Shrine grounds, as well as the landscaping in the area.
Out on Domain Road, work continues on the installation of the dual tram/bus platforms.
Edmund Herring Oval (EHO) Demolition
As mentioned last week, we’re all but done on the breakout of the main hard surface on EHO. All that remains is the roadway that is in place, as well as the base that currently sits underneath the old substation on EHO. This is progressively being dismantled and removed, to be taken off site and re-used elsewhere. Once its gone, we’ll break out the final section of concrete base that it was sitting on.
Friday Flashback
For today’s Friday Flashback we are travelling back to November 2021 and a cross section look at Anzac Station. This logistic void in the station roof stretched down from surface, past the concourse level and down to the base slab and provides us with a good look at the scale of the structure underneath St Kilda Road.

Have a great long weekend
Thanks, Rob
Great folk music and pizza
Some of the more observant of you may have noticed the line marking trucks last night. They were here to mark our car bays.

The weather was actually OK but alas, there were no traffic management people to assist them. It seems they must have exhausted all their shifts managing the traffic on our footpath over the last week waiting for an asphalt truck that never arrived.
Unbelievable
I am a local resident at The Botanica that has been heavily involved in the Metro Tunnel Project.
I am VERY frustrated by their inability to simply arrange regular lawn mowing. I understand that there is a bit of a demarcation issue but I was shocked to hear them say the other day that this is the most difficult part of the project – the handover to various bodies.
REALLY?? Arranging handover to councils is harder than the tunneling and construction – there must be something wrong with what you are trying to handover??
One part of the plan going forward is based on
I gave up and simply mow the lawn when I have time, usually on a Sunday morning – happy to have others come and help, even bring me a cafe late 🙂
If you are unhappy with the ongoing car and maintenance, feel free to send them an email to
MetroTunnel@railprojects.vic.gov.au

Jan and I met with CYP again on Wednesday – see attached
A few things to note, some from that meeting and some from subsequent meetings.
You may have noticed that our garden underwent a massive change today. Dead plants were replaced with other plants.
I never like being flippant on safety matters, but I think that closing one lane of St Kilda Rd, moving the bikes onto that lane, closing our footpath and moving the peds on to the bike lane…because of dangerous wheelbarrows and shovels may have been over the top.
Four hours work here in sixty seconds
Oh – yes they are still planning to plant five elm trees here….so the garden will need to be dug up for that.
Looks like they have managed to remove some of the dead plants. Smoko now
Feel free to offer them advice
Good afternoon everyone,
Welcome to our Friday look-ahead for construction activities in and around Anzac Station next week.
The rain last night means that the asphalting that was to happen on Thursday night couldn’t go ahead and will now happen tonight Friday 31 May
We’ll be working from the Toorak road tram stop heading north towards Bowen Lane.
If time permits, while the asphalt crews are out on site, we’ll also asphalt the bike lane adjacent to the Albert Road Station entrance – we’ll also look to asphalt the path on Domain Road adjacent to Melbourne Grammar, which should see the path reopen early next week.
Works next week
Albert Road Reserve forecourt and Station Entrance (Works until 1am)
This week we poured the concrete for the stairs that are adjacent to the Albert Road Reserve station entrance (next to the Windsor Oak in the park) as well as the concrete base directly next to the entry. No surprise that next week is pavers, pavers and more pavers – with the crews working their way along. We expect to see a mid-week concrete pour on the forecourt, followed by – you guessed it. More pavers.
Shrine Entrance and Domain Road (Works until 1am)
Because we can’t get enough of paving, next week we’ll pour the first part of concrete slab around the station entrance on the Shrine of Remembrance side to be closely followed by bluestone paving.
A heads up that we’ll also start demolishing the hardstand where the big white covered canopy was, this will be using excavators with hammers, as will allow works to commence on the footpath on this eastern side and the landscaping leading up to the Shrine grounds
Out on Domain Road, the tram platform base is complete with works to start next week on the tram platform structure.
Edmund Herring Oval (EHO) Demolition
Nothing new at EHO, with the breakout of the hard-stand continuing this week, we’ll also continue the removal the substation from Edmund Herring Oval. This will be taken away in parts, and as mentioned previously, at least one of these parts is an oversized load – which means it will need to be removed from site after-hours to comply with VicRoads requirements. No set date on this at the moment, but I’ll advise when this is happening.
Centre Island – St Kilda Road
The fresh new look for the central island is now in place, adding a nice touch of greenery to the area. Following tonight’s asphalting, we’ll have the green light for City of Melbourne to come through and plant the trees within the central median. Tree planting on the western side will be carried out by City of Port Phillip, we’ll advise when we have some dates for this planting.
Footpath RectificationStarting next Monday we’ll be in front of The Botanica during the day to rectify some low-points in the footpath asphalt. While we do this, pedestrian traffic will be temporarily diverted into the bike lane. Once we finish these works, we’ll be able to open the bike lane and open the St Kilda Road on-street parking in front of Botanica (400 St Kilda Road)
Friday Flashback
For today’s Friday Flashback we are heading to the intersection of Bowen Lane and St Kilda Road, where in March 2019, our clam shell excavator was digging the 20m deep diaphragm walls that form the station box.

Have a great weekend
Thanks, Rob

This digger was there yesterday but gone today – click on the link below to find out HOW
You must be logged in to post a comment.