Good news is that today they have poured the concrete where our driveway goes. Next step is waterproofing and then backfill. So all great progress.
That’s the good news…the bad news is that Chiller #1 is underway and it looks massive

Good news is that today they have poured the concrete where our driveway goes. Next step is waterproofing and then backfill. So all great progress.
That’s the good news…the bad news is that Chiller #1 is underway and it looks massive
A few people noticed this comment from CYP the other day …
“Next week the team will break out the previous kerb line and footpath in front of 390 St Kilda Road to prepare a temporary road surface for the re-orientation of Botanica’s St Kilda Road driveway out towards Bowen Lane. By late next week the driveway should be switched onto this new alignment. “
What does it mean? CYP are drawing some diagrams but essentially it will something like this
This will occur late this week
I know that if you can only exit via Bowen Lane it means a crazy path to South Melbourne. Don’t shoot the messenger
A new white tram was spotted being tested on the tracks near Anzac Station this week. Capacity is quite low but able to turn around in short spaces
Good morning everyone,
I hope everyone took the opportunity to get out into yesterday’s glorious sunshine after what can only be described as a miserable week of weather.
That is a not-so-subtle segue into the impact that the rain has had on the work out on site. The team have lost a huge amount of time to the weather this week and the overnight works that have been happening last week will unfortunately need to roll into the following week. While we recognise that this will roll directly into the 24/7 works starting on the 27th November – unfortunately it is unavoidable, as it is critical that the tram track infrastructure within the site is ready to connect into the infrastructure that we will be constructing while trams are shut down from the 27 November to the 17 December.
I’ve included a copy of the notification will go out on Monday to local residents advising of the extension to the works.
Once again the table of activities is contained below, but it is essentially the same activities that we have notified previously, but were unable to complete due to the weather.
Anzac Station entrance construction – Tram Interchange
On the station platform, the works next week will continue to be focussed on the laying of bluestone pavers. The question has been raised with the team about the planting of the new trees that will be a feature of the new tram platform. On the advice of arborists, the trees will be planted in Autumn next year rather than during the hotter summer months (after the past week of weather we’ve had this doesn’t ring true, but the advice is that the warmer months ahead will impact on the long term health of the future trees) Works on the station kiosk will also continue, with the installation of cladding around the kiosk.
On the canopy itself, the skylight flashing and final works on the architectural finishes on the underside of the canopy will all be underway next week.
Surface Works
The new track continues to make its way out from the platform to both the north and the south. Next week will see more track laid and concrete poured to the north of the tram platform, especially now that the backfill around the ventilation structures has largely been completed.
On the north-west corner of Park Street works have begun to construct the final legacy design for a kerb outstand and tram pole installation. The future kerb line extends out further from the existing kerb and this extended kerb line is currently being constructed, along with one of the tram wire poles that will be required during for the new tram alignment. To construct this extended kerb the left turn from Park Street into St Kilda Road has now been temporarily closed, this left turn will reopen ahead of the closure of the northbound lane of St Kilda Road to ensure access is maintained to the buildings along this section of St Kilda Road.
Station box construction
Underground, the team have completed both the eastern and western sections of track slab adjacent to the new tram platform. On the platform itself, we’ll be pouring the concrete for the wearing slab of the platform, while also continuing with our steelwork in preparation for the future platform screen doors. Escalators 1 and 2 are being installed next week, these sit adjacent to the freshly poured stairs linking the concourse level to the platform.
Shrine Entrance
The Shrine entrance continues to work away over in the corner of the site – installation of formwork is ongoing next week as is the steel fixing for the capping beam on top of the piles, this all ahead of the final stage of excavation, which is expected to commence in early December.
Extended Hours Works:
The works listed below are those that will extend overnight next week. At this stage of the program, all these works are likely to extend for the duration of the week.
If you are having issues with the noise outside during the nights – call 1800 105 105.
They will entertain relocations if needed as a last resort.
You may have also noticed that they cannot work if there is any rain….so you could take matters into your own hands and use one of these TOY water pistols. I doubt they can tell the difference between rain and water from this.
Good evening everyone,
Apologies for the delayed look ahead. It appears this didn’t send properly on Friday afternoon – with any luck this one arrives in your inboxes.
There has been a lot of change out on site recently with the site now divided by the new section of southbound lane of St Kilda Road. This has allowed the us to shift our barriers onto what was the previous southbound lane and begin to breakout the old traffic lane to lay new tram tracks and lay the new road alignment adjacent to these tracks. Thankyou to everyone for you patience as we tied in the new section of the road, the significant amount of rain did not help matters, but the new lane is now open and we’re pushing ahead.
Next week will see a number of key activities run up until 10pm – During the week just gone, we wrapped up activities at 8pm, but the weather is not looking kind, and it is more than likely that these will need to continue all the way until 10pm.
Anzac Station entrance construction – Tram Interchange
The footprint of the new tram interchange will begin to expand significantly over the next few weeks as the team begin to pour the concrete foundations of the platform itself. The platform extends from just near the top of Albert Road, all the way down beyond the new kiosk that has been constructed and is now in the process of being fitted out. The team are also getting up underneath the canopy to get some works done on the underside of the canopy, while at ground level, the first sections of glass for the balustrades around the oculus began to be installed this week and will continue into next week.
Next week will also see more progress on the kiosk, with the glass installed for the future kiosk and the installation off some of the cladding around the outside of the kiosk.
Some of these works will continue out to 10pm including works on the underside of the canopy and the installation of the new cladding on the kiosk.
Surface Works
Outside the platform, the new sections of tram tracks continue their progress through site on the eastern side. Now that we’ve taken the old southbound lane of St Kilda Road and made some room on the western side of the canopy, you’ll start to see more tram track work in this section as well as installation of the new tram poles. We are quickly approaching the deadline of the 27 November, when we switch off the power to the tram lines, buses replace trams and we begin the 24/7 works to break out the existing tracks and realign them to connect in with the new sections of tram alignment around the new platform. Like this week, next week some activities will extend out to 10pm to ensure we are ready for the 27 November. The platform and new sections of track need to be ready for this critical date, so over the coming weeks more activities will extend out to 10pm. Activities you’ll see on site next week are similar to those you’ve seen to date, with excavators doing earthworks, tram track laying, asphalting, concrete pours.
The ventilation shafts will also continue to get some attention next week, the concrete pours continuing for the northern shafts are complete, connecting them to the station roof. We’ll see same at the southern end next week before waterproofing and backfill commences on both.
Station box construction
The big development inside the station box is the start of the construction of the stairs from concourse level down to platform level. The frame for the future pedestrian elevator has also been installed. We’ve included a photo this week on the first section of the formwork for the new stairs.
Shrine Entrance
Next week at the Shrine entrance over near Domain Road will see the start of the steel fixing for the new section of roof. Once the roof is installed, the main excavation down to the future base slab will commence.
Regards, Rob and Christian
The Botanica Committee would like to invite you to join us for a Shared Christmas Breakfast
Date: Sunday December 18, 2022
Time: 7.45am- 10 am
Venue: The Botanical Hotel, 169 Domain Road, South Yarra
Cost: $40 per person
MENU:
On Arrival: 1 glass of Prosecco, Mimosa cocktail or orange juice.
Shared to the Table:
Guests selection of:
Or
Finish with: Tea or Coffee
Book online by 3/12/22: https://tinyurl.com/BotanicaXmas
If any difficulty booking online, Margaret (ph 0409 691 203) will be in the foyer on Thursday November 24th between 5pm-6pm to assist.
Someone followed a car into the upper car park last week and stole a scooter…. Be aware of lurkers, but also be careful
You must be logged in to post a comment.