Be aware that an evacuation drill be running tomorrow morning on the CYP site.
It is a practice only
Be aware that an evacuation drill be running tomorrow morning on the CYP site.
It is a practice only
I’ve had a few queries, so let me add a bit more to the story.
When we did the survey earlier in the year, we had 20 people respond and 4 of them said they expect to buy an EV in the next 2 years and another 5 in the 2-5 year time period.
The solution we are installing will allow up to 30 car bays to be connected, we expect that this will be sufficient for at least 5 years.
It is possible that some owners may wish to add a charger to their bay even if they do not buy an EV. This will make rental apartments for attractive for some tenants. Regardless we feel we are installing enough capacity 5 years.
We can expand the capacity to all car bays if required with further investment. We only envisage doing this when we are getting close to the 30 bay limit.
While the EV world is changing quickly, the backbone, the main cost of what we are installing, is mainly basic cables, it is the chargers that owners will install that will evolve most over time. So I expect that little of the common infrastructure will become dated.
You will see very little difference in the carpark. There will be some cabling up high and some boxes installed in our switchboard room.
No owner is being forced to install cabling and charger to their bay. If you do not want one, that is fine.
The current estimates for installation are $2400 plus GST for cabling and $1850 plus GST for a charger. So about $4700 inc GST.
The installation will be a bit like installing a general power point with an extension cable and each individual bay will be assessed by an electrician when you request a connection.
The chargers we are recommending today are JetCharge Chargemates. They work with all EVs sold in Australia. The chargers that can be installed at any time must be compliant with our system.


You can see the ‘power point’ with cover in this picture. That gives you an idea of the size of the charger. EV owners then have a special cable (that comes with their car) running from this device to their car.
Happy to answer any questions
The Committee has decided to install the basic infrastructure for charging electric vehicles (EVs) at a cost of approx. $35K. It will be installed in May.
Some things to note
As I have personally ordered an EV, I stood aside when the Committee voted on this matter.
Good afternoon everyone,
We hope you’ve been having a lovely week.
We are writing today with our next weekly construction lookahead.
Next week will be a shorter week than usual with the Easter long weekend. Works will stop on Thursday, with some works to decommission the large crane commencing from the following Tuesday. We will provide an update on the crane works next Thursday.
Anzac Station entrance construction – Tram Interchange
All eight of the station canopy legs that are connected to the pedestals at concourse level have now been installed in the oculus. After Easter, the four remaining legs will be installed.
This week, the first of the timber rafters and steel spline beams have been delivered to site, with the first of their installation underway. This work will continue next week.
Station box construction
No change to the works going on underground next week. Precast over track exhaust (OTE) installation continues, along with the framework that will form the platform doors. Installation of the precast sections of the future station platform are underway. The precast segments will be lowered into the station box until 10pm, while preparation works ahead of their installation will continue overnight. This activity is located entirely at platform level, and is unlikely to generate high noise at surface after 10pm.
Internal walls and permanent columns continue to be constructed in the station box, moving from south to north, as well as continuing the construction of the headwall that connects the station box to the tunnels. These works will involve steelfixing, formworking and concrete pours. As with all concrete pours, they must be completed continuously, and may run over normal construction hours.
As per the construction notice, steel fixing will continue in the station box 24/7.
Plunge columns will continue to be removed, as well as firewall shotcreting, heading from south to north in the station box. Works on the plunge columns will continue within the station box until 10pm, and preparation works for the firewall shotcreting will continue on night shift. These activities are unlikely to generate high noise at surface level.
As mentioned in last week’s update, the crane on surface will be required for use up until 10pm on work nights. The void in the south box continues to be closed up – and as a result a smaller crane has been mobilised in the northern section of site and will begin to be used to lower pre-cast segments into the northern void. This northern void will transition to become the main access down into the station box. The larger crane will be demobilised and taken from site prior to the Easter later this month. There will be times when both the large crane and the new smaller crane will be used on surface until 10pm at the same time.
Today we’ve included a photo of the progress of the platform construction down at the base of the station box. The team are making good progress as they construct the platform from south to north. Once the full platform is constructed, a capping slab of concrete is poured.
Surface Works
Surface breakout at the northern and middle sections of site have been progressing well this week. Below is a detailed run down of works to occur next week.
These works will generate periods of high noise and the works will be carried out during normal working hours.
In addition to the surface works listed below, waterproofing and screeding in the area will continue. Non-Destructive-Digging trucks – also known as sucker trucks – will be used on site to clean out any debris in the strip of reinforced steel prior to concrete being poured in the sections of delayed pour strip.
| Saturday 9/4 | Monday 11/4 | Tuesday 12/4 | Wednesday 13/4 | Thursday 14/4 |
| Spray and cleanout of stage 2 delayed strip pourCovered access construction through stage 2Stage 2 backfilling | Stage 1 D-Wall demolition ongoingStage 1 waterproofing ongoingStage 2 upstand demo ongoingStage 2 delayed pour strip ongoing | Stage 1 D-Wall demolition ongoingStage 1 waterproofing ongoingStage 2 upstand demo ongoingStage 2 delayed pour strip ongoing | Stage 1 D-Wall demolition ongoingStage 1 waterproofing ongoingStage 2 upstand demo ongoingStage 2 delayed pour strip ongoing | Stage 1 D-Wall demolition ongoingStage 1 waterproofing ongoingStage 2 upstand demo ongoingStage 2 delayed pour strip ongoing |
Thanks,
Rob and Jordan



Good afternoon everyone,
We hope you’ve been having a lovely week.
We are writing today with our next weekly construction lookahead.
Anzac Station entrance construction – Tram Interchange
If you’ve walked past the site this past week you will have seen that the first of the green canopy legs have been installed in the oculus. Due to their size, the legs are delivered overnight, and then installed during the day. Next week, canopy leg delivery and installation will continue. The first sections of the wooden canopy will also arrive to site next week for installation. We’ve included a picture today of one of the legs being lifted into place by crane.
Station box construction
No change to the works going on underground next week. Precast over track exhaust (OTE) installation continues, along with the framework that will form the platform doors. Installation of the precast sections of the future station platform are underway. The precast segments will be lowered into the station box until 10pm, while preparation works ahead of their installation will continue overnight. This activity is located entirely at platform level, and is unlikely to generate high noise at surface after 10pm.
Internal walls and permanent columns continue to be constructed in the station box, moving from south to north, as well as continuing the construction of the headwall that connects the station box to the tunnels. These works will involve steelfixing, formworking and concrete pours. As with all concrete pours, they must be completed continuously, and may run over normal construction hours.
As per the construction notice, steel fixing will continue in the station box 24/7.
Plunge columns will continue to be removed, as well as firewall shotcreting, heading from south to north in the station box. Works on the plunge columns will continue within the station box until 10pm, and preparation works for the firewall shotcreting will continue on night shift. These activities are unlikely to generate high noise at surface level.
As mentioned in last week’s update, the crane on surface will be required for use up until 10pm on work nights. The void in the south box continues to be closed up – and as a result a smaller crane has been mobilised in the northern section of site and will begin to be used to lower pre-cast segments into the northern void. This northern void will transition to become the main access down into the station box. The larger crane will be demobilised and taken from site prior to the Easter later this month. There will be times when both the large crane and the new smaller crane will be used on surface until 10pm at the same time.
Surface Works
Surface breakout at the northern end of site has been progressing well this week. Below is a detailed run down of works to occur next week.
These works will generate periods of high noise and the works will be carried out during normal working hours.
In addition to the surface works listed below, waterproofing in the area will continue.
| Monday 4/4 | Tuesday 5/4 | Wednesday 6/4 | Thursday 7/4 | Friday 8/4 | Saturday 9/4 |
| Concrete screed pour Stage 1Loadout fill Stage 1Loadout styrene blocks stage 1 and 2Demolition of timber walkway in stage 2 | Loadout styrene blocks stage 1/2Loadout fill stage 1Breakout Stage 2 protection slabDemolition of timber walkway in stage 2 | Covered access construction through stage 2 | Covered access construction through stage 2Spray and cleanout of stage 2 delayed strip pour | Covered access construction through stage 2Spray and cleanout of stage 2 delayed strip pourBackfill of stage 2 area commence | Spray and cleanout of stage 2 delayed strip pourCovered access construction through stage 2Stage 2 backfilling |
Traffic detector loop maintenance – Tuesday 5 April
On Tuesday evening, maintenance work will take place on the detector loop system at the eastbound intersection of Park Street and St Kilda Road. For the duration of these works, Park Street eastbound will be closed between Wells Street and St Kilda Road, with a detour in place via Wells Street and Dorcas Street.
The works are anticipated to take only a few hours, and while most of the works will not be impactful, some concrete sawcutting will be required to expose the detector loop system. This will be completed at the beginning of the works.
We’ve included the notification that was distributed to the area to this email for you for reference.
Thanks
Rob and Jordan


As we mentioned yesterday, the station will have line green… Installed today

You may have spotted a couple of images released of Anzac Station today. As I understand, the Minister wanted to get these out before CYP start erecting the steel!!

This one shows (left of screen) some vents similar to ‘our’ vents and chiller plants. I am assured that we will now have some decent trees shielding us from the chiller plant.
They have been given feedback that the high roof will give very little weather coverage for tram users. The lime green has also not been a popular decision.

This is the concourse level, one level below the street and one level above the train platform. There will be plenty of light The tram lines are either side of this area.
Good afternoon everyone,
We hope you’ve been keeping well.
We are writing today with our next weekly construction lookahead.
Anzac Station entrance construction – Tram Interchange
A lot of progress has been made this week in the tram interchange, most notably the feature stairs have been poured at the northern end of the oculus, and the escalators have been installed at the southern end.
Next week, steelfixing will continue on the pedestrian bridges over the oculus. Steelfixing in this area will continue until 10pm on work nights until the bridges are poured, which is currently scheduled for Tuesday.
Next week, work will continue to strip the formwork from the feature stairs, as will the installation of glazing on the lifts.
Set up for the canopy columns will also begin next week, with the first of the installation scheduled for late next week.
Station box construction
Precast over track exhaust (OTE) installation continues, along with the framework that will form the platform doors. Installation of the precast sections of the future station platform are underway. The precast segments will be lowered into the station box until 10pm, while preparation works ahead of their installation will continue overnight. This activity is located entirely at platform level, and is unlikely to generate high noise at surface after 10pm.
Internal walls and permanent columns continue to be constructed in the station box, moving from south to north, as well as continuing the construction of the headwall that connects the station box to the tunnels. These works will involve steelfixing, formworking and concrete pours. As with all concrete pours, they must be completed continuously, and may run over normal construction hours.
As per the construction notice, steel fixing will continue in the station box 24/7.
Plunge columns will continue to be removed, as well as firewall shotcreting, heading from south to north in the station box. Works on the plunge columns will continue within the station box until 10pm, and preparation works for the firewall shotcreting will continue on night shift. These activities are unlikely to generate high noise at surface level.
As mentioned in last week’s update, the crane on surface will be required for use up until 10pm on work nights.
Today, we’ve included a picture at platform level looking south. In this image you can see on the left the first of the platform installed. On the right, you can see the over track exhaust system being installed, with the steel framework for the platform doors in front.
Platform screen doors will be installed at each of the five new stations on the project. You can see a quick explainer on them via the link below:
Surface Works
Surface breakout at the northern end of site has been progressing well this week. Below is a detailed run down of works to occur next week.
These works will generate periods of high noise and the works will be carried out during normal working hours.
In addition to the surface works listed below, waterproofing in the area will continue, as well as formwork and steelfixing for the delayed strip pour.

Thanks
Rob and Jordan


You must be logged in to post a comment.