As I said…

At the AGM last night I mentioned that CYP were going to put some sound proofing up around that noisy piece of plant out the front. They have done it today.

I must say that it is not quite what I expected…

Yep – those blue panels are the soundproofing!?!?!

Important Metro Tunnel updates

I have various bits of important news…

Street trees

When this is all done we will be getting street trees back out the front…but it seemed like for some reason, it was decided that we’d rather have one less tree.

The gap that was to be left was in case the City of Port Phillip decided to put a bike hoop in there one day.

I didn’t out to popular vote in the building but I decided on my own that people would rather an elm than a bike rack.

Today I was told by Rob Mair…Alan and his team have come up with a configuration to get the full quota of trees back in front of Botanica. While it still needs final approval from Heritage Victoria, we have checked in with HV who have indicate that they have no issues with reinstating the tree that was removed between the Development Plan design and the Interim Design.

Vibration

The special bits of equipment have now been installed in the plant on Edmund Herring Oval and they are hoping it will have a positive impact on the terrible vibration.

Trucks

We are getting fewer trucks as most are now going on the agreed routes. Still quite a few speeding but certinaly fewer trucks.

Noisy ventilation unit

People on the front of the building will have noticed a massive ventilation unit that has recently appeared. It pumps fresh air into the station box but it is VERY noisy. They have agreed to install sound mats around it tomorrow morning.

See you tonight

Botanica AGM and Info night

Don’t forget that the AGM / Information night will be held tomorrow evening at 6pm – via Zoom

The Zoom link is here

You can try the link any time – you should simply get a message saying that the meeting does not start until 6pm tomorrow.

The first part is for Owners AND Renters – I will cover the Metro Tunnel work and the Fire sprinkler work.

The second part of the meeting is for Owners only – we will do a ‘roll call’ at that time.

For owners that are not attending, I encourage you to complete the attached proxy form. You can email to Leon at Civium or just drop it in my letterbox (702).

Proxy form is below

More CYP news

Good afternoon everyone,

As construction is continuing on the Metro Tunnel Project during the current Stage 4 restrictions, we recognise that in the residential buildings you have limited opportunities to get out of your home while construction work continues outside and many of your residents are working from home.

More than ever before we are looking for opportunities to limit the impacts of our works during the planning phase, however there will be times where the works will be noisy during the day.

Over the course of the Stage 4 restrictions, we will be trialling sending out a short weekly email update to help give you a better idea of what is coming up in the week ahead, with a focus on those works that might be disruptive.

We know many of you are sharing this correspondence with your building tenants through your normal channels – if you’d like us to add your building managers to this list, just let us know.

As you’re all no doubt aware, construction is always subject to change depending on the weather or progress of individual activities – all the information provided is as accurate as possible when we send it out.

Please Note: While this email address is monitored throughout the day during business hours, if you have an urgent issue, please be sure to contact us via 1800 105 105. This will ensure that your query is responded to in a timely manner.

ANZAC STATION WEEKLY LOOK AHEAD 

1.       Tunnelling 

Works will carry on as normal inside the acoustic shed. Currently, tunnelling is progressing well and the first TBM Millie is approaching Punt Road, with Alice not far behind.

2.       Anzac Station entrance – Shrine of Remembrance 

CFA piling has started around the perimeter of the new station entrance, with the piling rig now in place. The piling works that were underway in this area previously were deeper bored piles, this CFA piling will not be as noisy as the previous bored piles. 

3.    Tram Interchange Construction 

Piling is now complete on Tram Box construction site, we’re finished in this area for now – we’ll come back to this area in November to start excavation.

4.    Middle Box Roof Construction 

The final section of the Anzac Station Roof is being prepared. The temporary deck has been installed that we’ll use to support the pour of the final section of the roof. We’ve also laid form ply on top, which the roof slab will be cast against.

Next week we’ll start steel fixing and we’ll be using hand tools on the D-wall to prepare the tie in points. Preparations for the D-wall tie ins will be happening on Saturday. These works are expected to be completed in normal Saturday construction hours, however, depending on weather may run a bit later.

5.    Middle Box Excavation 

There is currently a lot of activity in this area.  Excavation under the roof is about 70% complete. We stopped excavation for a little while as we put together the latest addition to the site, the crawler crane. We’ll later use this crane to lower the steel and other materials down onto the excavated concourse level. Excavation has now recommenced. We have also added additional ventilation as we go further along our concourse excavation – we’ll be putting up some noise attenuation around this new vent addition in the following week.

Works on sections of the D-wall will be ongoing inside the excavation and are only expected to generate low levels of noise underneath the roof slab.

Thanks,

Rob, Dan and Jordan

Ventilation Unit

A couple of you have asked about this unit that has recently appeared….here is the offical line

 The team looking after the excavation under the deck have had to install additional ventilation while they are further underneath the concourse level.

You can see it circled in the picture below (Vision courtesy of Gary’s livestream) It will pump air down a specially created void directly next to the unit.

They’ll test it over the next two days and see how effective it is as a secondary ventilation unit – If it is effective, then they’ll use it for the remainder of the excavation (roughly 3 weeks)

We’ll also keep an eye on the noise it generates, we’ve added in provision for scaffolding to go around it and noise attenuation attached.  I’ll keep you posted on the test.


Thanks, Rob

Live vision – another view

I am testing another camera with live vision from my balcony. It is not so good at night but pretty sharp during the day and closer up.

The bad news at the moment is that the address changes each day, so you need to search on Google for “GaryBuck2 Youtube” and hopefully it will be there as ‘live now’

Today it should be here all day…..and there is a lot happening out there today.

Want to test Zoom before the AGM??

A few people have said that they are a bit nervous using Zoom for our AGM next week. It is not too hard, I’ve set up a test meeting for people to experiment with.

Test 1

If you click on this link any time, it will take you through the whole process but you won’t see anyone else.

Test 2

If you click on this link at 6:30pm tonight, I will be there and you will be able to see me and talk /listen.

During the AGM

During our AGM you will have to identify yourself at the start of the meeting but then you will then be able to have your video off (so no-one can see you) and have your audio off (so no-one can hear you)….if you wish

The trucks are back

Evening all,

Just a quick note to advise that the team on site has reported that VicRoads signage near the M1 entrance suggests that a section of Batman Avenue will be closed this evening from 10pm.
This may affect traffic routes and trucks may need to revert to using St Kilda Road. The team on site will monitor any closure and revert to the normal traffic route as soon as possible.


Thanks,

Metro Tunnel Project Team.

I can’t see it on the VicRoads site…mention of outage from 23/8 in tunnel?