Category Archives: St Kilda Rd living

Metro Rail – Summary of dates

The previous post had lots in it…here is a few of the key things to me

  • In the first few months of 2017, we will see lots of action.  New tram stop, Domain Rd closed, Bromby St opened
  • In second half of 2017 we will see tram /road / bike lanes moved to the ‘other side’ and trees go.
  • Early 2018 we will see the ‘open hole’.  It will be a big hassle but work will be mainly during daylight and go for about 18 months
  • Mid 2019 – An acoustic shed will minimise our noise / dust but work will go 7/24 for 18 months.
  • End 2021 – Our pain will be “over” and the road back to final config
  • 2026 – all systems go

Essentially the hassle will go for FIVE years from the start of 2017…not great but better than I thought previously.

Metro Rail – November update with timeline

Jan and I met with Metro Rail this week.  We met with

  • James Tonkin (Director of Communications & Stakeholder Relations)
  • Simon Adams (Domain Station Precinct Manager)
  • Jacqueline Novoselec (Senior Communications & Stakeholder Relations Advisor).

They provided the attached detailed pack (2016-11-mm-presentation-20161109-botanica) and spent a couple of hours with us discussing many of the issues in detail, especially the timeline.  I stressed to MMRA that everyone is trying to plan around the tunnel and we need a timeline.  Obviously it is not possible to be 100% definitive but the information below is the best estimate today.

Our engagement is strong, they are always keen to meet on site at Botanica and are very open and frank.

This is my version of the timeline for ‘early works’ plus tunnel construction

Late 2016

  • Work near the Shrine corner has commenced
  • Eight juvenile trees will go
  • Metro Rail have worked hard to keep two large trees in the compound area despite higher cost.

First half 2017

  • Bromby St will re-open around March in preparation for Domain Rd closure
  • Minor work in Bowen Cres on services relocation (telco lines, etc)
  • Before Anzac Day
    • New permanent Tram Super Stop on city side of Toorak Rd
    • Some plane trees will go for this stop
    • Number 8 trams start running on new route
  • Domain Road closed shortly after
  • Sewer work commences
    • Will be large shaft in Domain Rd (Closed section) and Albert Rd

Second half 2017

  • More sewer work
  • Expect preferred tunnel and station contractors announced by September 2017
  • Re-configure St Kilda Rd outside Botanica
    • One car lane, one tram lane and one bike lane in each direction
    • Outside Botanica, those lanes will be on opposite side of the road. They will sweep back to our side of the road near Albert Rd
    • The station box will be immediately on our kerb edge
    • Trees will go on both sides of the road
    • We will continue to have driveway access, except minor, well advised times.

Early 2018

  • Tunnel and Station Contractor mobilization
  • Construction of Station Box
    • Stage 1
      • Will be large  uncovered hole
      • Day work only
      • Will take roughly 18 months
      • Wall will be done via Diaphragm construction (https://www.youtube.com/watch?v=wUlQyiHfex0) Should be less intrusive than pile driving
      • See Cut and Cover pictures in attachment
      • Hole will go from our kerb edge past the middle of road

Mid 2019

  • Construction of Station Box
    • Stage 2
      • Acoustic shed built
      • Continuous 7/24 operation
      • Will take roughly 18 months

2021

  • Construction materially complete
  • Road back to final config
  • Advanced trees replanted

 

2022-2025

  • Final fit out / testing / civil work

 

2026

  • Operational

Apartment for sale

I understand that apartment 209 is for sale.  According to the agent it is currently rented for around $400 pw and and the asking price is $480,000.

Contact is  Jason Wedge at Biggin Scott on 0411 432 520

I have no interest at all in the apartment but people often ask me if there are places for sale in the building, so I thought I’d post this for general interest.

 

Metro Rail – Good news on trees

Metro Rail have just released this document – it answers questions from the panel on whether the rail tunnel will go under or over the CityLink tunnel….and about the tree replacement.

Not yet a done deal but this sounds much better than before!!  I have asked that it is tightened a bit further so that we don’t have demarcation between City of Melbourne and City of Port Phillip.  I’d hate to see one side flourishing and the other side struggling.

The tree info is in the second part of this document

065-rfi-12-9-16-i-domain-parklands-and-st-kilda-rd-boulevard