More on CYP

Summary of activities this week in the south

You will notice that D-wall demolition works will continue on top of the southern station box with the hammer and excavator working from north to south throughout this week.

Following this stage, we will continue the clean out of the delayed pour strip in this area with NDD sucker trucks in operation this week and going into next week.

Towards the end of this week, there will be some form reo pour with concrete pouring in those sections that have been cleaned out.

This will be the bulk of the works in this zone but do let us know if you have any further questions.

Happy to assist wherever possible.

Best regards

Rob and Christian

Advertisement

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s