CYP Update – Road closure on Thursday

Good afternoon everyone,

We hope you’ve all been keeping well.

We are writing today with our next weekly construction update

Please note: While this email address is monitored throughout the day during business hours, if you have an urgent issue, please be sure to contact us via 1800 105 105. This will ensure that your query is responded to in a timely manner.

ANZAC STATION WEEKLY LOOK AHEAD

Please be aware that Monday is an RDO. There will be some tunnelling related activity ongoing, but no other civil work will be occurring on Monday.

TBM Retrieval, Reassembly and Relaunch Preparatory Works

The tunnelling team continues to work 24/7 in preparation of the relaunch of TBMs Millie and Alice. Gantry pieces of the TBMs are being pulled back through the completed tunnel from the Eastern Portal, as work reassembling TBM Millie progresses.

The team at Edmund Herring Oval are also working to prepare for the TBM relaunch, with fabrication works, maintenance and repairs ongoing at the slurry treatment plant.

In the station box, the team is currently working to demolish the shifting way, which helped launch the TBM towards the Eastern Portal on the first drive. These works may be noticeable during the day while the shed doors are up, but the team will work to ensure that the noise stays within the shed after hours.

You may have noticed that we are currently storing some of the TBM pieces outside of the acoustic shed. The tunnelling team may need to do some minor works on these pieces up until 10pm. These pieces will be transferred to inside the acoustic shed during the week commencing Monday 23 November.

South Box Construction

Construction of the concourse slab is continuing underground. The second of 10 concrete pours for the concourse slab was completed on Tuesday, and is now curing. Next week, the team will commence the steelfixing for the third concourse pour. This will be the same process as has happened for the past two pours, with steel deliveries coming to site and being lowered into the void for installation.

The team will also apply a blinding layer of concrete for the slab on Tuesday. Crews will continue finishing works for this blinding pour up until 4am, but as this will be under the roof slab, is not expected to cause any disruption. We’ve attached a picture which shows a few stages of building the concourse slab – the image shows part of the completed concrete slab, some of the steelfixing, and the excavation.

Additionally, the south box team will be loading out material from the concourse excavation until 4pm tomorrow.

Anzac Station Entrance – Shrine of Remembrance

Mechanical, Electrical and Plumbing works continue at the Shrine of Remembrance entrance, as the team prepares to start the construction for the base slab.

Tomorrow the team will continue work to prepare for two blinding layers of concrete that will be poured next week. There will be some short periods of breakout tomorrow, and into early next week, as part of this work.

Next week, the team will complete the blinding layer pours of concrete, before they complete waterproofing and scabbling works to prepare for steelfixing to begin.

Anzac Station Entrance – Tram Box

Excavation continues for the eventual tram/station interchange entrance on St Kilda Road.

You may have noticed this week that the first of the breakout of the piles occurred. This activity will occur intermittently during the excavation of this entrance, and is expected to generate periods of high level noise.

Next week, the team will be installing ground anchors into the retaining wall. If you have a view over the site, you may also start to see red/orange struts arrive. These will be installed in this area of excavation to support the corner of the wall to the future Albert Road entrance. These struts will be a feature of this area of site for the coming year or so. We’ve attached a picture of support strutting, which is the same kind that will be used during the tram box excavation

Pedestrian Path Closure – Corner Domain Road and Shrine Grounds

On Wednesday, the stretch of footpath through our site that connects the Shrine Grounds to Domain Road will be closed. This closure will allow the project team to perform works related to tunnelling activities. Pedestrian access in the area will be maintained via a detour. We’ve attached a map that outlines the detour to this email.

St Kilda Road Southbound and Albert Road (North and South) Closures

On Thursday, there will be three road closures in the Domain Precinct – one on St Kilda Road (southbound), one on Albert Road North and one on Albert Road South. These closures will be to allow for the installation of traffic signage at the new Anzac Station site gate on St Kilda Road southbound to allow trucks to exit the site, and to allow for the replacement of faded linemarking on St Kilda Road southbound, Albert Road North and Albert Road South. Pedestrian access won’t be affected during any of these closures, and local driveway access will be maintained.

A hard copy works notification will be distributed with more information on these works next week.

Thanks,

Rob, Dan and Jordan

Christmas brunch – simpler version

Some people had trouble with the ‘pretty’ version on their phones. Here is the simple version….

The Committee would like to invite you to Join us for a Botanica Christmas Brunch

Date:  Sunday December 13, 2020

Time: 10.00am- 12 noon

Venue: Giro D’Italia Restaurant

           401 St Kilda Rd, Melbourne

Cost: $33 per person***

***  includes: 1 glass of Prosecco & tea/coffee or juice.

Tap or Sparkling water  & Choice of :

  • Muesli with Fruit & Yogurt
  • Big breakfast – Toast, Eggs, Bacon, Tomato & Mushrooms
  • Eggs on Toast – (with Bacon if desired)
  • Avocado Toast –(with or without eggs )
  • Pancakes with Berries & Mascarpone
  • Extras: Juice/Tea/Coffee $4.00         Prosecco  $6 per glass

RSVP by 8/12/20: Margaret Ph 0409 691 203

Join in our Christmas Wreath Competition:

                                Winner announced at the breakfast!                               

Cup weekend puzzle

Albert Road Reserve is getting a makeover courtesy of CYP / Metro Tunnel. This is the last design pics that I saw.

As I understand, the grand opening will have a string quartet and dog grooming – not sure where else you can have your dog shorn whilst listening to a string quartet??

My confusion is that the current state of the site. Here is a current photo.

I think it will be easier to pick a winner of the Cup than work out how the recently installed poles will fit in to this setup.

Other details

That horrible beeping noise

That noise that sounds like an alarm and has been going on for more than 24 hours has been reported to the EPA. Hard to work out where it is coming from – we thought it may have been from the top of the Ace Carpark. We asked the people selling those apartments to check…they said that they did. The noise goes on

Thanks Trish for doing the calls

A days fews of peace and quiet

Tomorrow is an RDO, Tuesday is a holiday and Wednesday is another RDO. More details below


ANZAC STATION WEEKLY LOOK AHEAD

Please be aware that Monday is an RDO, Tuesday is the Melbourne Cup Public Holiday and Wednesday is also an RDO. Tunnelling related activities will continue both underground and at EHO, but there will be no other civil works on these days.

TBM Retrieval and Reassembly Works

On Wednesday and Thursday morning, the final TBM parts will be delivered from the Eastern Portal to the Anzac Station site. These parts are over height, meaning they’ll travel to Domain using an alternate route. Visit https://metrotunnel.vic.gov.au/disruptions/transport-changes/oversized-deliveries for information on oversized deliveries and associated road closures. 24/7 works will continue underground to pull the gantry pieces through the completed tunnel and continue assembling the TBMs.

General maintenance and refurbishment works are also continuing 24/7 at the Edmund Herring Oval tunnelling support site, with filter press cleaning, STP repairs, asphalting and trenching for new slurry pipes all happening next week.

South Box Construction

Under the roof of the south box we’re continuing the concourse level construction in sections through the process of excavation, installing formwork and steel reinforcements before pouring concrete. The team is on track to complete 4/10 pours in 2020.

Currently we’re now onto the steel fixing for the second section as we aim to pour on 9 November.

As with the first section, this will involve the delivery of steel and use of the crawler crane while works continue underground. Steel fixing works will continue up until 10pm weekdays and 6pm on Saturdays underneath the roof slab and are not expected to generate much noise.

Anzac Station Entrance – Shrine of Remembrance

Excavation to base slab level is now complete for the Shrine of Remembrance station entrance. Next week, works to construct the base slab will continue with mechanical, electrical, plumbing works scheduled. These MEP works are expected to continue for most of the month.

Anzac Station Entrance – Tram Box

Excavation is underway for the main Anzac Station entrance, the tram interchange. You’ll notice machinery loading trucks with excavated soil, and the wheel wash installed on the station roof, which is being used for all trucks exiting the site. Next week, hand railing will be set up along the boundary of the excavation area, and mesh will be installed for upcoming shotcrete works.

Piles will be progressively broken back as the excavation continues, however in this initial excavation there is only a short period of pile breakout scheduled for late next week, around two hours in total. This is expected to generate intermittent periods of high-level noise.

We’ve attached a photo of the excavation for the station entrance on the Shrine side of the shed. The tram interchange construction follows the same bottom-up construction methodology; we excavate all the way down before the base slab is constructed, followed by the roof slab. This differs from the top-down method used to build the station box, wherein the roof slab was constructed first. Those with a view over the site will see a similar process happening between the acoustic shed & St Kilda Road in the coming months as the tram interchange station entrance starts to take shape.

Have a great weekend – we hope you pick a winner on Tuesday!

Thanks,

Rob, Jordan & Dan

Lots of tunnel news and pictures

Some of the main points to note

  • The trucking company is now using some decent tracking. It allows them to track a truck going ‘off approved routes’ and to detect speeding trucks. They noted that it has changed the behaviour of the drivers
  • The first TBM will commence before Xmas and finish in May.
  • Second TBM will commence in February and finish in late June
  • This means that the period of two TBMs is Feb-May
  • Work / meetings are happening this week to avoid unacceptable vibration when two TBMs are running
  • Public discussion on legacy design (including Chiller plants) will not happen this year.