If you want to know more – register for this zoom session

If you want to know more – register for this zoom session


Good afternoon everyone,
We’ll get right to the point – Next week marks the start of two weeks of overnight works within the precinct – Our apologies in advance for the disruption that will follow, but as we’ve outlined before – we absolutely cannot miss the start date for the shutdown of the tram corridor on Sunday 27th of November.
In the sections below I’ve briefly outlined the daytime activities next week – with a more detailed table that breaks down the overnight activities scheduled in for next week.
Anzac Station entrance construction – Tram Interchange
In yet another step towards a functioning tram platform, we’ve now got the first of the bluestone pavers laid down. I’ve included a photo of the first section of the new pavers going down, particularly as this will be a key activity that will continue up until 10pm in the leadup to the 27th November – and potentially overnight depending on progress. The reason this is such a key activity is that the entire footprint of the new tram platform features bluestone pavers, requiring a significant amount of work and coordination to ensure they are laid in time. Over the next few weeks the tiling crews will be a continued presence on the platform. The glass balustrades are also being installed around the opening in the tram platform looking down onto the tram platform. On top of the canopy roof, the team need to do the final elements of waterproofing, to support this activity, we’ll have another two scaffold towers erected at either end of the canopy. The roof of the canopy will be a busy place over the next three weeks as this is our last chance to access the roof before we kick off the 24/7 works, and ultimately commission the new platform.
Surface Works
Either side of the platform, the most obvious addition is the new track that is slowly extending out from the platform. Next week a lot of the preparation works will move into the southern section as the tracks make their way to the south end of the site. The backfill around the ventilation structures will also be finished off next week and the teams will start installing the bracketry inside the precast elements of the ventilation shafts, before the cladding is then installed.
Elsewhere around site CitiPower will be doing some work to decommission redundant light poles ahead of the 24/7 works at the end of November. We’ve attached a copy of their notification regarding these works.
There will also be some work to decommission redundant pits on the footpath of the pedestrian crossing at the Park Street tram stop on St Kilda Road. The footpath and crossing will remain open while these works are underway with fencing in place.
Station box construction
Underground the station box team are continuing to make good progress, the track slab construction is nearly complete on both the eastern and western sides. The platform will soon have new set of stairs leading up to the concourse, with the steel fixing for the stairs nearly complete and a pour scheduled in for next week.
Shrine Entrance
Next week over at the Shrine of Remembrance entrance the team will doing some work to break back piles ahead the pouring of a capping beam over the top. Steel fixing for the roof of this section of the entrance will also continue, while in those completed sections we’ll kick off some of the waterproofing works
Extended Hours Works:
The works listed below are those that will extend overnight next week. The coloured squares indicate the days that the listed activity will be continuing. We’ll have additional supervision on site to ensure that we minimise any unnecessary noise, however all these activities will continue through the night. Activities such as hammering and sucker trucks are not permitted during the night, and other activities such as paver cutting will be stopped at 10pm.
As always, there is a chance that these days may slip or shift – but this represents the teams current thinking around which crews will be working in each location, each evening.

Regards, Rob and Christian
Thanks to the 33 people who completed the survey. A few quick snapshots


A few particular matters that were raised
See below – but nothing until THURSDAY
Good afternoon everyone,
In addition to the Melbourne Cup public holiday, over the next five days we will be observing a construction shutdown period which means that no construction works will be occurring onsite until next Thursday 3 November.
With a short week, this will be a brief summary of activities for next week. That being said, there will be works occurring at the end of next week including some out of hour works with an overview of these activities outlined below.
Anzac Station entrance construction – Tram Interchange
When construction activities recommence next Thursday, works will continue surrounding the tram platform including trenching to install drainage and conduits for electrical and communication services to the platform.
Glass balustrades will be installed around the central mezzanine overlooking the underground station box and works on the canopy fascia and under flashing to the skylights will continue.
Cladding will be applied to the external surface of the kiosk and internal services to the kiosk will continue to be installed.
These works surrounding the tram platform and kiosk will continue out of normal construction hours until 10pm on weekdays and until 6pm on Saturdays, to ensure that critical works to the tram platform are complete for the start of tram realignment works in November.
Surface Works
Next week, between 8pm, Thursday 3 November and 5am Friday 4 November, the team will be shifting concrete barriers along the southbound lane of St Kilda Road to provide new access points into the construction site.
To undertake these works safely, this will require a closure of the southbound lane of St Kilda Road between Dorcas Street and Toorak Road and will need to occur overnight, outside of high traffic periods.
Through the centre of the construction site, works to install tram tracks and tram infrastructure such as overhead poles will continue in the preparation for the tram realignment works in November.
At the northern and southern ventilation and services shafts, waterproofing, backfilling and installation of utility services will recommence next week.
Around the perimeter surfaces of the structures, cladding will be installed. Due to recent inclement weather, works on and around these structures will continue outside of normal construction hours until 10pm on weekdays and 6pm on Saturdays.
Station box construction
Within the lower levels of the station box, finishing elements of blockwork installation are almost complete and fit out works are continuing.
Mechanical, electrical and plumbing works are continuing and works to fitout the lifts and vertical transportation are underway.
Shrine Entrance
Next week at the Shrine entrance over near Domain Road we will continue steel fixing for the new section of the top-down roof. Once the roof is installed, the main excavation down to the future base slab will commence.
Regards, Rob and Christian
TO THE RESIDENT / TRADER
412 St KILDA ROAD, MELBOURNE
NOTIFICATION OF FULL ROAD CLOSURE
BOWEN CRESENT/ QUEENS LANE INTERSECTION TO ST
KILDA ROAD/ BOWENS CRESENT INTERSECTION.
Date: 03/11/2022
You are advised that the associated building works need to occur on with a dry run
involving a crane set up on 03/11/2022 from 7am till 6pm and as such this notice
serves as information of the likely impact of this activity.
These works are a component of the refurbishment at 412 St Kilda Road. The works
involve the use of a mobile crane operating from 7am – 6pm and will result in a full
road closure. The machinery will operate for 1 day – During normal construction
hours.
In case of inclement weather or unforeseen delays, if we are not able to set up on
these dates the set up may occur on 26/10/2022 and 27/10/2022
Although the works are substantial, every very effort will be made to minimize impact
to businesses and the general public. The following treatments will apply:
• Pedestrian access will be maintained via opposite footpath(s)
• Access to building car parks are to be maintained
• Access to all properties will be maintained.
The refurbishment works for this site was never going to be an easy task however,
the contractor will attempt to minimize the impact of these building works and
apologises for any inconvenience that may be caused.
Although the works will be difficult for local traders and residents, your co-operation
will be greatly appreciated.
Thank you.
Daily FDC contact:
Jake Harry 0438 069 187


Good evening everyone,
Apologies for the delayed look ahead. It appears this didn’t send properly on Friday afternoon – with any luck this one arrives in your inboxes.
There has been a lot of change out on site recently with the site now divided by the new section of southbound lane of St Kilda Road. This has allowed the us to shift our barriers onto what was the previous southbound lane and begin to breakout the old traffic lane to lay new tram tracks and lay the new road alignment adjacent to these tracks. Thankyou to everyone for you patience as we tied in the new section of the road, the significant amount of rain did not help matters, but the new lane is now open and we’re pushing ahead.
Next week will see a number of key activities run up until 10pm – During the week just gone, we wrapped up activities at 8pm, but the weather is not looking kind, and it is more than likely that these will need to continue all the way until 10pm.
Anzac Station entrance construction – Tram Interchange
The footprint of the new tram interchange will begin to expand significantly over the next few weeks as the team begin to pour the concrete foundations of the platform itself. The platform extends from just near the top of Albert Road, all the way down beyond the new kiosk that has been constructed and is now in the process of being fitted out. The team are also getting up underneath the canopy to get some works done on the underside of the canopy, while at ground level, the first sections of glass for the balustrades around the oculus began to be installed this week and will continue into next week.
Next week will also see more progress on the kiosk, with the glass installed for the future kiosk and the installation off some of the cladding around the outside of the kiosk.
Some of these works will continue out to 10pm including works on the underside of the canopy and the installation of the new cladding on the kiosk.
Surface Works
Outside the platform, the new sections of tram tracks continue their progress through site on the eastern side. Now that we’ve taken the old southbound lane of St Kilda Road and made some room on the western side of the canopy, you’ll start to see more tram track work in this section as well as installation of the new tram poles. We are quickly approaching the deadline of the 27 November, when we switch off the power to the tram lines, buses replace trams and we begin the 24/7 works to break out the existing tracks and realign them to connect in with the new sections of tram alignment around the new platform. Like this week, next week some activities will extend out to 10pm to ensure we are ready for the 27 November. The platform and new sections of track need to be ready for this critical date, so over the coming weeks more activities will extend out to 10pm. Activities you’ll see on site next week are similar to those you’ve seen to date, with excavators doing earthworks, tram track laying, asphalting, concrete pours.
The ventilation shafts will also continue to get some attention next week, the concrete pours continuing for the northern shafts are complete, connecting them to the station roof. We’ll see same at the southern end next week before waterproofing and backfill commences on both.
Station box construction
The big development inside the station box is the start of the construction of the stairs from concourse level down to platform level. The frame for the future pedestrian elevator has also been installed. We’ve included a photo this week on the first section of the formwork for the new stairs.
Shrine Entrance
Next week at the Shrine entrance over near Domain Road will see the start of the steel fixing for the new section of roof. Once the roof is installed, the main excavation down to the future base slab will commence.
Regards, Rob and Christian
There are some orange poles out the front that mark the divide between the tram tracks and the road. Some days I go out and see that a few are missing or strewn about.
I’ve sometimes wondered how it happens – now I know
A very detailed pack below. Some details
Also worth noting is the efforts with new trees. You can see from this image that there will be trees on the platform

To assist their growth (on top of the concrete station roof) they have installed what is called Strata Vault. See below.

Will be done by 10pm – just talked to them and checked
You must be logged in to post a comment.