Jan and I attended the regular meeting with CYP today – nothing really new but some useful updates
See the chart above that gives the high level schedule for the next 12 months.
Takeaways for The Botanica
- Before Xmas they will build the guide walls on our front door step
- They will finish the D Walls in the Northern box in v early January.
- They will then walk the cranes over to us and start on our D Wall panels. That will be at night – 1 or 2 nights
Other info presented included
- The cable work under our footpath will continue in January but the footpath will be re-instated before Xmas
- There will be a covered walkway in front of us and 390 St K Rd from January
- Bowen Lane to Albert Rd should be open by Monday at latest, hopefully Saturday
- They are using some sophisticated truck tracking system that helps ensure that trucks use approved routes, don’t speed and generally do the right things.
- Air and vibration monitoring indicates all under legal limits
- No noise info presented
There will be a site shutdown from December 22 to January 9 – but the 1800 105 105 number will still be manned


We have had issues with cockies eating part of the building facade for some years. The good news is that we have a solution but the installation will not start until mid-January.