MMRA are interested in helping to facilitate a process with the Tunnels and Stations contractor (once appointed) to explore the potential for senior engineers and other tunnel workers (many expected from overseas) to talk to people in our building who want to rent out their apartment
Category Archives: Metro Tunnel
Metro Rail – Contact info
Metro Rail already have a 1800 in umber in place for queries. They are very happy for Botanica residents to call the number and make operational queries.
This includes things like “Is the drilling in Bowen Crescent today related to Metro Rail, how long will it go?”
Feel free to call 1800 551 927 (Monday to Friday, 9am to 5pm).
Once the construction begins in 2018 there will be a different process and I’d expect it to be a 24 hour facility.
Metro Rail – Summary of dates
The previous post had lots in it…here is a few of the key things to me
- In the first few months of 2017, we will see lots of action. New tram stop, Domain Rd closed, Bromby St opened
- In second half of 2017 we will see tram /road / bike lanes moved to the ‘other side’ and trees go.
- Early 2018 we will see the ‘open hole’. It will be a big hassle but work will be mainly during daylight and go for about 18 months
- Mid 2019 – An acoustic shed will minimise our noise / dust but work will go 7/24 for 18 months.
- End 2021 – Our pain will be “over” and the road back to final config
- 2026 – all systems go
Essentially the hassle will go for FIVE years from the start of 2017…not great but better than I thought previously.
Metro Rail – November update with timeline
Jan and I met with Metro Rail this week. We met with
- James Tonkin (Director of Communications & Stakeholder Relations)
- Simon Adams (Domain Station Precinct Manager)
- Jacqueline Novoselec (Senior Communications & Stakeholder Relations Advisor).
They provided the attached detailed pack (2016-11-mm-presentation-20161109-botanica) and spent a couple of hours with us discussing many of the issues in detail, especially the timeline. I stressed to MMRA that everyone is trying to plan around the tunnel and we need a timeline. Obviously it is not possible to be 100% definitive but the information below is the best estimate today.
Our engagement is strong, they are always keen to meet on site at Botanica and are very open and frank.
This is my version of the timeline for ‘early works’ plus tunnel construction
Late 2016
- Work near the Shrine corner has commenced
- Eight juvenile trees will go
- Metro Rail have worked hard to keep two large trees in the compound area despite higher cost.
First half 2017
- Bromby St will re-open around March in preparation for Domain Rd closure
- Minor work in Bowen Cres on services relocation (telco lines, etc)
- Before Anzac Day
- New permanent Tram Super Stop on city side of Toorak Rd
- Some plane trees will go for this stop
- Number 8 trams start running on new route
- Domain Road closed shortly after
- Sewer work commences
- Will be large shaft in Domain Rd (Closed section) and Albert Rd
Second half 2017
- More sewer work
- Expect preferred tunnel and station contractors announced by September 2017
- Re-configure St Kilda Rd outside Botanica
- One car lane, one tram lane and one bike lane in each direction
- Outside Botanica, those lanes will be on opposite side of the road. They will sweep back to our side of the road near Albert Rd
- The station box will be immediately on our kerb edge
- Trees will go on both sides of the road
- We will continue to have driveway access, except minor, well advised times.
Early 2018
- Tunnel and Station Contractor mobilization
- Construction of Station Box
- Stage 1
- Will be large uncovered hole
- Day work only
- Will take roughly 18 months
- Wall will be done via Diaphragm construction (https://www.youtube.com/watch?v=wUlQyiHfex0) Should be less intrusive than pile driving
- See Cut and Cover pictures in attachment
- Hole will go from our kerb edge past the middle of road
- Stage 1
Mid 2019
- Construction of Station Box
- Stage 2
- Acoustic shed built
- Continuous 7/24 operation
- Will take roughly 18 months
- Stage 2
2021
- Construction materially complete
- Road back to final config
- Advanced trees replanted
2022-2025
- Final fit out / testing / civil work
2026
- Operational
Serious prep work starting – Metro Rail
You may have already seen this info but I thought it is worth posting for wider distribution.
This link gives details of upcoming work near us. This is preparatory work for the Metro Rail project. It is not mentioned in this but I also understand some major work will also occur in Bowen Crescent.
Tram update
Metro Rail have issued this short video to explain what is intended to happen with the various tram routes. See it here
Metro Rail – Final submission
Metro Rail are making their final submission tomorrow – here is a copy of it.
mmra-iac-closing-submissions-7-10-2016
Covers their position on moving the Domain station, doing cavern vs cut and cover, S Yarra Station…..
Happy reading – feel free to hear it in person at the Mercure Hotel in Spring St at 10am
Metro Rail – Good news on trees
Metro Rail have just released this document – it answers questions from the panel on whether the rail tunnel will go under or over the CityLink tunnel….and about the tree replacement.
Not yet a done deal but this sounds much better than before!! I have asked that it is tightened a bit further so that we don’t have demarcation between City of Melbourne and City of Port Phillip. I’d hate to see one side flourishing and the other side struggling.
The tree info is in the second part of this document
065-rfi-12-9-16-i-domain-parklands-and-st-kilda-rd-boulevard
Metro Rail – Update
I’ve been away for a week and so I thought I’d better give everyone a quick update.
As I mentioned in my last update – the Botanica submission went in and seemed to be well received. Since then there have been a number of other submissions.
Probably the most interesting was one recommending that the station is located nearer the city, on the eastern side of St Kilda Rd near the Shrine. This would be MUCH better for us but my reading of the tea-leaves is that this is unlikely – possible but unlikely.
It is worth remembering something that our barrister told me several times, all submissions are based on their merit – it does not matter if it is mentioned once or a hundred times, once is enough. So it will be considered and we do not need to say anything additional.
At the AGM I mentioned that one of the key documents is something called the EPR’s. These form the basis of the contract with the tunneling companies and so are fundamental. A new version was released on Monday and the panel has asked for feedback. We will be submitting feedback if our domain experts deem it necessary. You will see that one of our experts (Terry Bellair) has already had a lot of his comments added to the document. You can see the full document if you click on the link below
mm-environmental-performance-requirements_iac-revision-3_trackedchanges
Metro Rail – Moment of truth
Well after many months of work – our day arrived today and “we” presented the Botanica submission to the Metro Rail Panel. I have attached our outline and the PowerPoint pack that one of our experts used.
Many thanks to the support from Jan, Jane, Jan, Alex, Veronica and Sandy.
It was a very long day (9am – 6pm) and all focused on Domain precinct. By the end of the day I was really pleased with our team of experts, lawyers and barrister. The issues we wanted raised were raised, our experts were subjected to intense cross examination…and survived …we were heard and listed to.
Well done Paul, Nick, John, Terry and Neville.
I have to add that the ‘noise guy’ for Domain was good but struggled badly under the cross examination. Also the planning guy for G12 / Domain was very disappointing. He didn’t understand the process and had not done sufficient work – it was clear to me and VERY clear to the panel.
Now we sit back and wait…well for a couple of weeks
16-09-16_draft-outline-of-submissions-botanica-owners-corporation-v1