Category Archives: Metro Tunnel

CYP update

See below – but nothing until THURSDAY

Good afternoon everyone,

In addition to the Melbourne Cup public holiday, over the next five days we will be observing a construction shutdown period which means that no construction works will be occurring onsite until next Thursday 3 November.

With a short week, this will be a brief summary of activities for next week. That being said, there will be works occurring at the end of next week including some out of hour works with an overview of these activities outlined below.

Anzac Station entrance construction – Tram Interchange

When construction activities recommence next Thursday, works will continue surrounding the tram platform including trenching to install drainage and conduits for electrical and communication services to the platform.

Glass balustrades will be installed around the central mezzanine overlooking the underground station box and works on the canopy fascia and under flashing to the skylights will continue.

Cladding will be applied to the external surface of the kiosk and internal services to the kiosk will continue to be installed.

These works surrounding the tram platform and kiosk will continue out of normal construction hours until 10pm on weekdays and until 6pm on Saturdays, to ensure that critical works to the tram platform are complete for the start of tram realignment works in November.

Surface Works

Next week, between 8pm, Thursday 3 November and 5am Friday 4 November, the team will be shifting concrete barriers along the southbound lane of St Kilda Road to provide new access points into the construction site.

To undertake these works safely, this will require a closure of the southbound lane of St Kilda Road between Dorcas Street and Toorak Road and will need to occur overnight, outside of high traffic periods.

Through the centre of the construction site, works to install tram tracks and tram infrastructure such as overhead poles will continue in the preparation for the tram realignment works in November.

At the northern and southern ventilation and services shafts, waterproofing, backfilling and installation of utility services will recommence next week.

Around the perimeter surfaces of the structures, cladding will be installed. Due to recent inclement weather, works on and around these structures will continue outside of normal construction hours until 10pm on weekdays and 6pm on Saturdays.

Station box construction

Within the lower levels of the station box, finishing elements of blockwork installation are almost complete and fit out works are continuing.

Mechanical, electrical and plumbing works are continuing and works to fitout the lifts and vertical transportation are underway.

Shrine Entrance

Next week at the Shrine entrance over near Domain Road we will continue steel fixing for the new section of the top-down roof. Once the roof is installed, the main excavation down to the future base slab will commence.

Regards, Rob and Christian

Another Bowen Cres closure

TO THE RESIDENT / TRADER
412 St KILDA ROAD, MELBOURNE
NOTIFICATION OF FULL ROAD CLOSURE

BOWEN CRESENT/ QUEENS LANE INTERSECTION TO ST
KILDA ROAD/ BOWENS CRESENT INTERSECTION.

Date: 03/11/2022

You are advised that the associated building works need to occur on with a dry run
involving a crane set up on 03/11/2022 from 7am till 6pm and as such this notice
serves as information of the likely impact of this activity.
These works are a component of the refurbishment at 412 St Kilda Road. The works
involve the use of a mobile crane operating from 7am – 6pm and will result in a full
road closure. The machinery will operate for 1 day – During normal construction
hours.
In case of inclement weather or unforeseen delays, if we are not able to set up on
these dates the set up may occur on 26/10/2022 and 27/10/2022
Although the works are substantial, every very effort will be made to minimize impact
to businesses and the general public. The following treatments will apply:
• Pedestrian access will be maintained via opposite footpath(s)
• Access to building car parks are to be maintained
• Access to all properties will be maintained.
The refurbishment works for this site was never going to be an easy task however,
the contractor will attempt to minimize the impact of these building works and
apologises for any inconvenience that may be caused.
Although the works will be difficult for local traders and residents, your co-operation
will be greatly appreciated.

Thank you.
Daily FDC contact:
Jake Harry 0438 069 187

What are those vents used for???

  • The round one is an inlet – It brings in outside air to the mechanical systems, so nothing will be discharged from it.
  • The middle one is an outlet – It is the over track exhaust, but also has battery/uninterruptable power supply (UPS) room exhaust in the event they are called on. During normal operations, the over track exhaust extracts heat locally from the air conditioner condensers which are onboard the train and braking devices of the stationary trains. In the unlikely event of a fire, this would be used to extract smoke from the trackway, platform and concourse.
  • The tall one is a tunnel ventilation system (TVS) inlet exhaust –The TVS shaft can either exhaust or supply depending on the requirements of the tunnel (two shafts – one supply and one exhaust). The TVS is an environmental control e.g provide fresh air within tunnel and discharges oncoming air from approaching trains. In the unlikely event of a fire, the TVS is designed to prevent smoke spreading and to maintain acceptable conditions in the non-incident tunnel.

CYP update

Good evening everyone,

Apologies for the delayed look ahead. It appears this didn’t send properly on Friday afternoon – with any luck this one arrives in your inboxes.

There has been a lot of change out on site recently with the site now divided by the new section of southbound lane of St Kilda Road. This has allowed the us to shift our barriers onto what was the previous southbound lane and begin to breakout the old traffic lane to lay new tram tracks and lay the new road alignment adjacent to these tracks. Thankyou to everyone for you patience as we tied in the new section of the road, the significant amount of rain did not help matters, but the new lane is now open and we’re pushing ahead.

Next week will see a number of key activities run up until 10pm – During the week just gone, we wrapped up activities at 8pm, but the weather is not looking kind, and it is more than likely that these will need to continue all the way until 10pm.

Anzac Station entrance construction – Tram Interchange

The footprint of the new tram interchange will begin to expand significantly over the next few weeks as the team begin to pour the concrete foundations of the platform itself. The platform extends from just near the top of Albert Road, all the way down beyond the new kiosk that has been constructed and is now in the process of being fitted out. The team are also getting up underneath the canopy to get some works done on the underside of the canopy, while at ground level, the first sections of glass for the balustrades around the oculus began to be installed this week and will continue into next week.

Next week will also see more progress on the kiosk, with the glass installed for the future kiosk and the installation off some of the cladding around the outside of the kiosk.

Some of these works will continue out to 10pm including works on the underside of the canopy and the installation of the new cladding on the kiosk.

Surface Works

Outside the platform, the new sections of tram tracks continue their progress through site on the eastern side. Now that we’ve taken the old southbound lane of St Kilda Road and made some room on the western side of the canopy, you’ll start to see more tram track work in this section as well as installation of the new tram poles.  We are quickly approaching the deadline of the 27 November, when we switch off the power to the tram lines, buses replace trams and we begin the 24/7 works to break out the existing tracks and realign them to connect in with the new sections of tram alignment around the new platform.  Like this week, next week some activities will extend out to 10pm to ensure we are ready for the 27 November.  The platform and new sections of track need to be ready for this critical date, so over the coming weeks more activities will extend out to 10pm.  Activities you’ll see on site next week are similar to those you’ve seen to date, with excavators doing earthworks, tram track laying, asphalting, concrete pours.

The ventilation shafts will also continue to get some attention next week, the concrete pours continuing for the northern shafts are complete, connecting them to the station roof. We’ll see same at the southern end next week before waterproofing and backfill commences on both.

Station box construction

The big development inside the station box is the start of the construction of the stairs from concourse level down to platform level. The frame for the future pedestrian elevator has also been installed. We’ve included a photo this week on the first section of the formwork for the new stairs.

Shrine Entrance

Next week at the Shrine entrance over near Domain Road will see the start of the steel fixing for the new section of roof. Once the roof is installed, the main excavation down to the future base slab will commence.

Regards, Rob and Christian

CYP – CRG update

A very detailed pack below. Some details

  • The VERY noisy occupation period will be from 1am Sunday November 27
  • The first 2-3 days will be the worst, but all three weeks will be noisy and 24*7 hour
  • There will be no trams operational and a bus replacement system. We will get more detail closer to the time
  • The cladding on our vents may happen before the occupation
  • If we have a lot of wet weather, then we there may be overnight work in the period November 7-19

Also worth noting is the efforts with new trees. You can see from this image that there will be trees on the platform

To assist their growth (on top of the concrete station roof) they have installed what is called Strata Vault. See below.

Bowen Cres closure 24/10/2022 – 25/10/2022

18 October 2022

TO THE RESIDENT / TRADER

412 St KILDA ROAD, MELBOURNE

NOTIFICATION OF FULL ROAD CLOSURE

BOWEN CRESENT/ QUEENS LANE INTERSECTION TO ST KILDA ROAD/ BOWENS CRESENT INTERSECTION.

Date: 24/10/2022 – 25/10/2022

You are advised that the associated building works need to occur on with a dry run involving a crane set up on 24/10/2022 – 25/10/2022 from 7am till 7pm and as such this notice serves as information of the likely impact of this activity.

These works are a component of the refurbishment at 412 St Kilda Road. The works involve the use of a mobile crane operating from 7am – 7pm and will result in a full road closure. The machinery will operate for 2 days.

In case of inclement weather or delays, if we are not able to set up up on these dates the set up may occur on 26/10/2022 and 27/10/2022

Although the works are substantial, every very effort will be made to minimize impact to businesses and the general public. The following treatments will apply:

•           Pedestrian access will be maintained via opposite footpath(s)

•           Access to building car parks are to be maintained

•           Access to all properties will be maintained.

The refurbishment works for this site was never going to be an easy task however, the contractor will attempt to minimize the impact of these building works and apologises for any inconvenience that may be caused.

Although the works will be difficult for local traders and residents, your co-operation will be greatly appreciated.

Thank you.

Daily FDC contact:

Jake Harry 0438 069 187

The Botanica Christmas breakfast

The Botanica Committee would like to invite you to join us for a Shared Christmas Breakfast

                        Date:  Sunday December 18, 2022

                        Time: 7.45am- 10 am

                         Venue: The Botanical Hotel, 169 Domain Road, South Yarra

                         Cost: $40 per person

 MENU:

On Arrival: 1 glass of Prosecco, Mimosa cocktail or orange juice.

Shared to the Table:

  • Granola, yoghurt, macerated berries
  • Seasonal Fruit, local honeycomb
  • Penny for Pound mini croissants and breakfast pastries

Guests selection of:

  • Poached eggs, avocado, goats curd, toasted seeds, Baker Bleu sourdough

Or

  • Eggs Benedict, smoked pork hock, poached eggs, espelette pepper, Hollandaise , pork crackle

Finish with:  Tea or Coffee

Book online by 3/12/22: https://tinyurl.com/BotanicaXmas 

If any difficulty booking online, Margaret (ph 0409 691 203) will be in the foyer on Thursday November 24th     between 5pm-6pm to assist.